5620 N WOODMAN AVE 91401

Certificate Information: 5620 N WOODMAN AVE 91401

Application / Permit
20016-10000-22154
Plan Check / Job No.
B20LA16210
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93:(3) SPECIAL CANTILEVERED COLUMNS WITH GRADE BEAMS
Permit Issued
Issued on 11/30/2020
Issuing Office
Current Status
CofC Issued on 4/16/2021

Permit Application Status History

Submitted 9/8/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 VARAND SARKISIAN
Corrections Issued 10/6/2020 VARAND SARKISIAN
Quality Review Completed 10/13/2020 HANS SANTIAGO
Plan Check Approved 11/2/2020 VARAND SARKISIAN
Issued 11/30/2020 APPLICANT
OK for CofC 2/26/2021 KENNETH ROBERTS
CofC Issued 4/16/2021 KENNETH ROBERTS

Permit Application Clearance Information

Tenant Habitability Plan Cleared 11/24/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/29/2020 Partial Inspection DANIEL VARNUM
Deputy Steel/Welding 1/11/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 1/15/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 1/20/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 1/20/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 1/20/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 1/20/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 1/21/2021 Approved JOE VELASQUEZ
Structural Steel Frame 1/21/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 1/21/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 1/22/2021 No Access for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 1/26/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 1/26/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 1/26/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 1/27/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 1/27/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 1/27/2021 Not Ready for Inspection JOE VELASQUEZ
Reinforced Concrete Frame 2/1/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 2/1/2021 Approved JOE VELASQUEZ
Wood Frame 2/1/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 2/4/2021 Approved JOE VELASQUEZ
Final 2/10/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 2/10/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 2/10/2021 Not Ready for Inspection JOE VELASQUEZ
Final 2/26/2021 OK for CofC KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 2/26/2021 Approved KENNETH ROBERTS