6107 E MYOSOTIS ST 90042
Certificate Information: 6107 E MYOSOTIS ST 90042
- Application / Permit
- 20016-10000-22110
- Plan Check / Job No.
- B20LA16154
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached garag to Accessory Dwelling Unit.
- Permit Issued
- Issued on 11/6/2020
- Issuing Office
- Current Status
- CofO Issued on 10/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/1/2020 | JOE VO |
| Corrections Issued | 10/7/2020 | JOE VO |
| Quality Review Completed | 10/21/2020 | MINYE PAK |
| Plan Check Approved | 11/4/2020 | JOE VO |
| Issued | 11/6/2020 | APPLICANT |
| CofO in Progress | 10/21/2021 | CRAIG VAUGHAN |
| Permit Finaled | 10/27/2021 | DEROLD HAUFF |
| CofO Issued | 10/27/2021 | DEROLD HAUFF |
| Permit Finaled | 10/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/27/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 10/27/2020 | ELAINE LEI |
| Sewer availability | Cleared | 10/27/2020 | ELAINE LEI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/23/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/23/2021 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 4/23/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 4/23/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 5/18/2021 | Corrections Issued | CRAIG VAUGHAN |
| PLUMBING-Rough | 5/18/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 6/18/2021 | Approved | COREY HUPP |
| Green Building Rough | 6/18/2021 | Approved | COREY HUPP |
| Rough-Elec/Plmb/HVAC | 6/18/2021 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 6/25/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 6/25/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 6/30/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/30/2021 | Approved | WILLIAM WREN |
| Final | 7/27/2021 | Corrections Issued | CRAIG VAUGHAN |
| Gas Test | 7/27/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 7/27/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 7/27/2021 | Approved | CRAIG VAUGHAN |
| Final | 7/30/2021 | Conditional Approval | CRAIG VAUGHAN |
| Green Building Final | 7/30/2021 | Approved | CRAIG VAUGHAN |
| Final | 8/2/2021 | Conditional Approval | CRAIG VAUGHAN |