925 E MILWOOD AVE 90291

Certificate Information: 925 E MILWOOD AVE 90291

Application / Permit
20016-10000-22004
Plan Check / Job No.
B20LA16107
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
New covered patio attached to (E) Garage.Rehab of (E) Garage building to Include relacement of windowns and doors (Size and location per existing or original, garage door),Electrical upgrade (outlet and car charging), Heating and cooling through wall unit (storage of antique car), New siding.per Engr design
Permit Issued
Issued on 1/14/2021
Issuing Office
Current Status
CofO Issued on 11/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 SAMUEL GONZALEZ
Corrections Issued 9/11/2020 SAMUEL GONZALEZ
Applicant returned to address corrections 12/15/2020 SAMUEL GONZALEZ
Applicant returned to address corrections 1/11/2021 LUKE GONZALES
Plan Check Approved 1/14/2021 LUKE GONZALES
Issued 1/14/2021 APPLICANT
Building Plans Picked Up 1/19/2021 APPLICANT
CofO in Progress 10/27/2022 JOHNNY MIRANDA
Permit Finaled 11/18/2022 DANIEL ORRANTE
CofO Issued 11/18/2022 DANIEL ORRANTE
Permit Finaled 11/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/1/2020 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 10/2/2020 SAUL GARCIA
Coastal Zone Cleared 11/12/2020 RUBEN VASQUEZ
Specific Plan Cleared 11/17/2020 BINDU KANNAN

Contact Information

Contractor Harrison Construction; Lic. No.: 917150-B 1121 MARCO PLACE      VENICE, CA 90291
Engineer Behshid,, Farshid; Lic. No.: S4585 4647 ENCINAS DR      LA CANADA, CA 91011

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/5/2021 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 5/20/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/20/2021 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 6/18/2021 Approved JACK MATTILLO
ELECTRICAL-Final 6/18/2021 Not Ready for Inspection JACK MATTILLO
Green Building Rough 6/18/2021 Approved JACK MATTILLO
Final 7/16/2021 No Access for Inspection JOHNNY MIRANDA
Footing/Foundation/Slab 7/16/2021 No Access for Inspection JOHNNY MIRANDA
Green Building Final 7/16/2021 No Access for Inspection JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/16/2021 SGSOV Not Ready JOHNNY MIRANDA
Smoke Detectors 7/16/2021 No Access for Inspection JOHNNY MIRANDA
ELECTRICAL-Final 7/20/2021 Approved JOHNNY MIRANDA
Final 7/27/2021 OK to Issue CofO JOHNNY MIRANDA
Footing/Foundation/Slab 7/27/2021 Approved JOHNNY MIRANDA
Green Building Final 7/27/2021 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 7/27/2021 Approved JOHNNY MIRANDA