6162 E OUTLOOK AVE 90042

Certificate Information: 6162 E OUTLOOK AVE 90042

Application / Permit
20016-10000-21997
Plan Check / Job No.
B20LA16101
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU 1 OF 2
Permit Issued
Issued on 12/14/2020
Issuing Office
Current Status
CofO Issued on 6/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/5/2020 APPLICANT
Assigned to Plan Check Engineer 10/1/2020 DANIEL YIP
Corrections Issued 10/5/2020 DANIEL YIP
Quality Review Completed 10/9/2020 ALLEN MANALANSAN
Building Plans Picked Up 10/14/2020 APPLICANT
Plan Check Approved 12/14/2020 DANIEL YIP
Issued 12/14/2020 APPLICANT
CofO in Progress 3/10/2022 COREY HUPP
CofO in Progress 3/10/2022 COREY HUPP
Permit Finaled 6/3/2022 DEROLD HAUFF
CofO Issued 6/3/2022 DEROLD HAUFF
Permit Finaled 6/3/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/26/2020 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/26/2020 ELAINE LEI
Sewer availability Cleared 10/26/2020 ELAINE LEI
Work Adjacent to Public Way Cleared 10/26/2020 ARMEN SARKISIAN
HPOZ Cleared 11/6/2020 KATIE DEBIASE

Contact Information

Contractor Gil And Sons Construction; Lic. No.: 1027547-B 2056 MARINE AVE      GARDENA, CA 90249
Engineer Tuchscher,, James Todd; Lic. No.: C77649 5503 E 2ND ST      LONG BEACH, CA 90803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/1/2021 Not Ready for Inspection COREY HUPP
Footing/Foundation/Slab 3/8/2021 Approved OSVALDO PARAMO
Pre-Inspection 3/8/2021 Corrections Issued OSVALDO PARAMO
Wood Frame 5/6/2021 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 5/14/2021 Corrections Issued COREY HUPP
Wood Frame 6/8/2021 Not Ready for Inspection CRAIG VAUGHAN
Wood Frame 7/1/2021 Approved COREY HUPP
Interior/Exterior Lathing 7/13/2021 Corrections Issued COREY HUPP
Insulation 7/21/2021 Approved COREY HUPP
Drywall Nailing 7/28/2021 Approved COREY HUPP
Final 10/13/2021 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 10/13/2021 Approved LILIANA PORTILLO
Final 10/25/2021 No Access for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/25/2021 SGSOV Not Ready OSVALDO PARAMO
Final 10/29/2021 Not Ready for Inspection COREY HUPP
SGSOV-Seismic Gas S/O Valve 10/29/2021 SGSOV Not Ready COREY HUPP
Final 11/10/2021 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 11/10/2021 SGSOV Not Ready OSVALDO PARAMO
Final 2/17/2022 Conditional Approval COREY HUPP
SGSOV-Seismic Gas S/O Valve 2/17/2022 SGSOV Approved COREY HUPP
Final 3/10/2022 OK to Issue CofO COREY HUPP
Final 5/3/2022 Corrections Issued JOAQUIN GREENOUGH
Special/Order Compliance 5/3/2022 Corrections Issued JOAQUIN GREENOUGH