6539 N BOBBYBOYAR AVE 91307
Certificate Information: 6539 N BOBBYBOYAR AVE 91307
- Application / Permit
- 20016-10000-21991
- Plan Check / Job No.
- B20LA16099
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING (E) DETACHED GARAGE INTO AN ADU CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 2/9/2021
- Issuing Office
- Current Status
- CofO Issued on 6/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2020 | FERNANDO FLORES |
| Corrections Issued | 9/9/2020 | FERNANDO FLORES |
| Plan Check Approved | 1/20/2021 | SHANGQIN XIE |
| Issued | 2/9/2021 | APPLICANT |
| Building Plans Picked Up | 3/1/2021 | APPLICANT |
| CofO in Progress | 6/10/2022 | TROY SANDERS |
| Permit Finaled | 6/10/2022 | JOHN JANSON |
| CofO Issued | 6/10/2022 | JOHN JANSON |
| Permit Finaled | 6/10/2022 | JOHN JANSON |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/14/2020 | RIDWAN HARDY |
| Address approval | Cleared | 12/29/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 12/29/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 12/29/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 12/29/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Levet Inc; Lic. No.: 1027447-B | 1110 SONORA AVE #101 GLENDALE, CA 91201 |
| Engineer | Kilpatrick,, David Albert; Lic. No.: S3142 | 1962 WILCOX CIR PLACENTIA, CA 92670 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/22/2021 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 3/15/2021 | Approved | TROY SANDERS |
| Pre-Inspection | 7/27/2021 | Partial Inspection | KRISTEN CAUSEY |
| Pre-Inspection | 7/27/2021 | Partial Inspection | RYAN SALAZAR |
| Pre-Inspection | 7/27/2021 | Partial Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 7/27/2021 | Partial Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/30/2021 | Approved | TROY SANDERS |
| HVAC-Rough | 7/30/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 7/30/2021 | Approved | TROY SANDERS |
| Underground Mechanical | 7/30/2021 | Approved | TROY SANDERS |
| Wood Frame | 7/30/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 8/3/2021 | Partial Approval | TROY SANDERS |
| Green Building Rough | 8/3/2021 | Not Ready for Inspection | TROY SANDERS |
| Wood Frame | 8/3/2021 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 8/11/2021 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 8/11/2021 | Approved | STEPHANIE SWANSON |
| Insulation | 8/11/2021 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 8/11/2021 | Partial Approval | STEPHANIE SWANSON |
| Drywall Nailing | 8/27/2021 | Corrections Issued | STEPHANIE SWANSON |
| Drywall Nailing | 8/30/2021 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/21/2021 | SGSOV Not Ready | TROY SANDERS |
| Final | 1/25/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 1/25/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 1/25/2022 | SGSOV Not Ready | DAVID SCANTLIN |
| Smoke Detectors | 1/25/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2022 | SGSOV Not Ready | TROY SANDERS |
| Final | 5/27/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 5/27/2022 | Not Ready for Inspection | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/27/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/27/2022 | Approved | TROY SANDERS |
| Final | 6/10/2022 | OK to Issue CofO | TROY SANDERS |
| Green Building Final | 6/10/2022 | Approved | TROY SANDERS |