10821 W BLOOMFIELD ST 91602

Certificate Information: 10821 W BLOOMFIELD ST 91602

Application / Permit
20016-10000-21849
Plan Check / Job No.
B20LA16017
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: By adding 1 SSCC at the South Elevation
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
CofC Issued on 5/18/2021

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/23/2020 VARAND SARKISIAN
Corrections Issued 10/1/2020 VARAND SARKISIAN
Quality Review Completed 10/5/2020 HANS SANTIAGO
Plan Check Approved 11/6/2020 VARAND SARKISIAN
Issued 2/17/2021 APPLICANT
OK for CofC 5/11/2021 KENNETH ROBERTS
CofC Issued 5/18/2021 RICKEY JACKSON

Permit Application Clearance Information

Tenant Habitability Plan Cleared 1/8/2021 ISMAEL HERNANDEZ
Hold Cleared 2/22/2021 JASON SHEETS

Contact Information

Contractor Sks Construction; Lic. No.: 720390-B 5104 GARDEN GROVE AVE      TARZANA, CA 91356
Engineer Shaolian,, Shahab Joseph; Lic. No.: C84155 5104 GARDEN GROVE      TARZANA, CA 91356

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/24/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 3/5/2021 No Access for Inspection JOE VELASQUEZ
Deputy Steel/Welding 3/5/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 3/8/2021 Approved JOE VELASQUEZ
Structural Steel Frame 3/8/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 3/8/2021 Corrections Issued JOE VELASQUEZ
Deputy Reinf. Concrete 3/9/2021 No Access for Inspection JOE VELASQUEZ
Insulation 3/12/2021 Approved JOE VELASQUEZ
Structural Steel Frame 3/12/2021 Approved JOE VELASQUEZ
Wood Frame 3/12/2021 Approved JOE VELASQUEZ
Interior/Exterior Lathing 3/16/2021 Approved JOE VELASQUEZ
Final 4/26/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 4/26/2021 Not Ready for Inspection JOE VELASQUEZ
Pre-Inspection 4/27/2021 Not Ready for Inspection JOE VELASQUEZ
Final 4/28/2021 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 4/28/2021 Not Ready for Inspection JOE VELASQUEZ
Final 5/11/2021 OK for CofC KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 5/11/2021 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 5/11/2021 Approved KENNETH ROBERTS