7823 N TUJUNGA AVE 91605
Certificate Information: 7823 N TUJUNGA AVE 91605
- Application / Permit
- 20016-10000-21671
- Plan Check / Job No.
- B20LA15910
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Addition to (E) detached garage and conversion of entire building to an ADU. Detached ADU per ordinance. All works per Wood Frame Prescriptive Provisions.
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- CofO Issued on 12/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | HELEN NGUYEN |
| Corrections Issued | 10/1/2020 | HELEN NGUYEN |
| Quality Review Completed | 10/13/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 10/22/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/23/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/28/2020 | HELEN NGUYEN |
| Applicant returned to address corrections | 1/27/2021 | HELEN NGUYEN |
| Plan Check Approved | 2/10/2021 | HELEN NGUYEN |
| Issued | 3/19/2021 | APPLICANT |
| CofO in Progress | 12/21/2022 | MATTHEW NELSON |
| CofO Issued | 12/24/2022 | MICHAEL SMITH |
| Permit Finaled | 12/24/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/6/2020 | ADRIAN CASTRO |
| Flood clearance | Cleared | 1/11/2021 | BRYAN GATHUKA |
| Eng Process Fee Ord 176,300 | Cleared | 1/20/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/20/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/11/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 5/19/2021 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 6/14/2021 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/30/2021 | Not Ready for Inspection | JOHN HAYES |
| FLOOD-Proofing Certificate | 7/30/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/30/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/10/2021 | Not Ready for Inspection | JOHN HAYES |
| FLOOD-Proofing Certificate | 8/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 8/10/2021 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 9/10/2021 | Partial Inspection | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/12/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 11/17/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 12/9/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 12/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 1/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 1/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| FLOOD-Proofing Certificate | 2/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/9/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/19/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/27/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| FLOOD-Elevation Certificate | 11/30/2022 | Approved | MATTHEW NELSON |
| Final | 11/30/2022 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/30/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 11/30/2022 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 11/30/2022 | Approved | MATTHEW NELSON |
| Final | 12/14/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/14/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 12/20/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 12/20/2022 | Approved | MATTHEW NELSON |
| HVAC-Final | 12/20/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 12/20/2022 | Approved | MATTHEW NELSON |
| Pre-Inspection | 12/20/2022 | Approved | MATTHEW NELSON |
| Service/Power Release | 12/20/2022 | Approved | MATTHEW NELSON |
| Final | 12/21/2022 | OK to Issue CofO | MATTHEW NELSON |