13178 W JUDD ST 91331
Certificate Information: 13178 W JUDD ST 91331
- Application / Permit
- 20016-10000-21560
- Plan Check / Job No.
- B20LA15837
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO A.D.U
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 10/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | JOE VO |
| Corrections Issued | 10/6/2020 | JOE VO |
| Quality Review Completed | 10/20/2020 | MINYE PAK |
| Plan Check Approved | 12/8/2020 | JOE VO |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 6/11/2021 | MICHEL ABAJAN |
| Permit Finaled | 10/12/2021 | MICHAEL SMITH |
| CofO Issued | 10/12/2021 | MICHAEL SMITH |
| Permit Finaled | 10/12/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/15/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/15/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2020 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/17/2021 | Approved | MICHEL ABAJAN |
| Underground Mechanical | 2/24/2021 | Partial Approval | MICHEL ABAJAN |
| Gas Test | 3/8/2021 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/8/2021 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Rough-Elec/Plmb/HVAC | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 3/15/2021 | Approved | JENNIFER RABUCHIN |
| Insulation | 3/18/2021 | Corrections Issued | JOHN HAYES |
| Insulation | 3/26/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 4/1/2021 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 6/10/2021 | Approved | MICHEL ABAJAN |
| Final | 6/10/2021 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 6/10/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/10/2021 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 6/10/2021 | Approved | MICHEL ABAJAN |
| Final | 6/11/2021 | OK to Issue CofO | MICHEL ABAJAN |