13178 W JUDD ST 91331

Certificate Information: 13178 W JUDD ST 91331

Application / Permit
20016-10000-21560
Plan Check / Job No.
B20LA15837
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO A.D.U
Permit Issued
Issued on 12/9/2020
Issuing Office
Current Status
CofO Issued on 10/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/3/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 JOE VO
Corrections Issued 10/6/2020 JOE VO
Quality Review Completed 10/20/2020 MINYE PAK
Plan Check Approved 12/8/2020 JOE VO
Issued 12/9/2020 APPLICANT
CofO in Progress 6/11/2021 MICHEL ABAJAN
Permit Finaled 10/12/2021 MICHAEL SMITH
CofO Issued 10/12/2021 MICHAEL SMITH
Permit Finaled 10/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/15/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/15/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 10/22/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/17/2021 Approved MICHEL ABAJAN
Underground Mechanical 2/24/2021 Partial Approval MICHEL ABAJAN
Gas Test 3/8/2021 Approved MICHEL ABAJAN
Interior/Exterior Lathing 3/8/2021 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/15/2021 Approved JENNIFER RABUCHIN
Green Building Rough 3/15/2021 Approved JENNIFER RABUCHIN
METHANE-Rough 3/15/2021 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 3/15/2021 Approved JENNIFER RABUCHIN
Shower Pan 3/15/2021 Approved JENNIFER RABUCHIN
Insulation 3/18/2021 Corrections Issued JOHN HAYES
Insulation 3/26/2021 Approved MICHEL ABAJAN
Drywall Nailing 4/1/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/10/2021 Approved MICHEL ABAJAN
Final 6/10/2021 Corrections Issued MICHEL ABAJAN
HVAC-Final 6/10/2021 Approved MICHEL ABAJAN
PLUMBING-Final 6/10/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/10/2021 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 6/10/2021 Approved MICHEL ABAJAN
Final 6/11/2021 OK to Issue CofO MICHEL ABAJAN