1346 W 83RD PL Units 1-3 90044
Certificate Information: 1346 W 83RD PL Units 1-3 90044
- Application / Permit
- 20016-10000-21487
- Plan Check / Job No.
- B20LA15792
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EXISTING ATTACHED GARAGE (231SF ZONING) & GUESTROOM TO BE CONVERTED INTO ADU IN EXISTING 2 STORY DUPLEX BUILDING
- Permit Issued
- Issued on 2/9/2022
- Issuing Office
- Current Status
- CofO Issued on 3/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | ADAM HEGAZI |
| Corrections Issued | 9/8/2020 | ADAM HEGAZI |
| Applicant returned to address corrections | 8/5/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 10/21/2021 | SINA KHOSRAVI |
| Applicant returned to address corrections | 11/20/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 1/7/2022 | AUNG SOE |
| Plan Check Approved | 1/10/2022 | AUNG SOE |
| Issued | 2/9/2022 | APPLICANT |
| CofO in Progress | 3/8/2023 | LILIANA PORTILLO |
| CofO in Progress | 3/8/2023 | HORACE FULTZ |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
| CofO Issued | 3/11/2023 | DEROLD HAUFF |
| Permit Finaled | 3/11/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 7/9/2021 | RENZ SORIANO |
| Address approval | Cleared | 7/12/2021 | RENZ SORIANO |
Contact Information
| Contractor | La Rocca Builders Inc; Lic. No.: 934161-B | 14320 VENTURA BLVD STE 724 SHERMAN OAKS, CA 91423 |
| Engineer | Sabzehzar,, Habib; Lic. No.: C50442 | 8180 N PRICE AVE FRESNO, CA 93720 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/8/2022 | No Access for Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 7/12/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/28/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 7/28/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/3/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/3/2022 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 8/3/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 8/3/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/27/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/27/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 9/27/2022 | Approved | LILIANA PORTILLO |
| Insulation | 9/27/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/27/2022 | Approved | LILIANA PORTILLO |
| Gas Test | 10/3/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 10/3/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/13/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 10/20/2022 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 10/26/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| Smoke Detectors | 10/26/2022 | Approved | LILIANA PORTILLO |
| Final | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 11/15/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | LILIANA PORTILLO |
| Pre-Inspection | 11/18/2022 | Partial Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/5/2023 | Corrections Issued | LILIANA PORTILLO |
| Final | 1/5/2023 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 1/5/2023 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/5/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/5/2023 | Approved | LILIANA PORTILLO |
| Final | 1/17/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/13/2023 | Approved | LILIANA PORTILLO |
| Final | 2/13/2023 | Conditional Approval | LILIANA PORTILLO |
| Service/Power Release | 2/13/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 2/15/2023 | OK to Issue CofO | LILIANA PORTILLO |
| Service/Power Release | 2/15/2023 | Approved | LILIANA PORTILLO |