2019-2021 S HILLCREST DR 90016

Certificate Information: 2019-2021 S HILLCREST DR 90016

Application / Permit
20016-10000-21446
Plan Check / Job No.
B20LA15736
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
INTERIOR REMODEL OF (2) DUPLEXES. 2 NEW WATER HEATERS, 2 NEW 100 AMPS MSP, REWIRE, RE-ROOF, ADD LAUNDRY TO EACH DUPLEX, ADD (1) BEDROOM TO EACH DUPLEX, RECONFIGURE (E) BATH, RELOCATE KITCHEN, NEW GAS METER TO EACH DUPLEX, NEW WINDOWS THRU OUT
Permit Issued
Issued on 11/3/2020
Issuing Office
Current Status
Permit Finaled on 9/22/2021

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 ADAM HEGAZI
Corrections Issued 9/8/2020 ADAM HEGAZI
Applicant returned to address corrections 10/1/2020 RACHEL BEYENE
Plan Check Approved 10/2/2020 RAHEL BEYENE
Issued 11/3/2020 APPLICANT
Building Plans Picked Up 11/12/2020 APPLICANT
Permit Finaled 9/21/2021 STUART CHAPMAN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Bc Home Builders; Lic. No.: 940362-B 3202 WEST WARNER AVENUE      SANTA ANA, CA 92704

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/16/2021 Not Ready for Inspection CRAIG VAUGHAN
Final 8/10/2021 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/10/2021 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 8/10/2021 Approved STUART CHAPMAN
Final 9/21/2021 Permit Finaled STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/21/2021 SGSOV Approved STUART CHAPMAN