3531-3531 1/2 E 6TH ST 90023
Certificate Information: 3531-3531 1/2 E 6TH ST 90023
- Application / Permit
- 20016-10000-21424
- Plan Check / Job No.
- B20LA15702
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) ONE STORY SINGLE FAMILY RESIDENCE TO CONVERT INTO ADU PER WFPP.
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/1/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/4/2020 | TSE MING HUANG |
| Corrections Issued | 9/6/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 12/15/2020 | ADAM HEGAZI |
| Plan Check Approved | 1/8/2021 | SAMUEL GONZALEZ |
| Issued | 1/25/2021 | APPLICANT |
| Building Plans Picked Up | 1/28/2021 | APPLICANT |
| CofO in Progress | 5/31/2023 | FREDDIE RIVERA |
| Permit Finaled | 7/1/2023 | DEROLD HAUFF |
| CofO Issued | 7/1/2023 | DEROLD HAUFF |
| Permit Finaled | 7/1/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/1/2020 | JUAN ASHTON |
| Roof/Waste drainage to street | Cleared | 10/1/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | JUAN ASHTON |
| Sewer availability | Cleared | 10/9/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 11/10/2020 | KURT CORRAL |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/8/2021 | Partial Inspection | ROBERT VORHIS |
| Deputy Drilled-In Anchors | 7/13/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 7/15/2021 | Corrections Issued | ROBERT VORHIS |
| Footing/Foundation/Slab | 1/10/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 2/2/2022 | Conditional Approval | ADAM ESCOTO |
| Footing/Foundation/Slab | 2/4/2022 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 2/16/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/16/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 3/29/2022 | Conditional Approval | FREDDIE RIVERA |
| Wood Frame | 3/29/2022 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 4/11/2022 | Partial Inspection | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 4/14/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 4/14/2022 | Partial Approval | FREDDIE RIVERA |
| Wood Frame | 4/14/2022 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/9/2022 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/9/2022 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/24/2022 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/24/2022 | Approved | FREDDIE RIVERA |
| Green Building Rough | 5/24/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/24/2022 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 5/31/2022 | Conditional Approval | FREDDIE RIVERA |
| Insulation | 5/31/2022 | Approved | FREDDIE RIVERA |
| Insulation | 6/3/2022 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 6/3/2022 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 6/3/2022 | Conditional Approval | FREDDIE RIVERA |
| Drywall Nailing | 6/8/2022 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Approved | FREDDIE RIVERA |
| Shower Pan | 7/19/2022 | Corrections Issued | FREDDIE RIVERA |
| Shower Pan | 7/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/4/2022 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/26/2022 | Corrections Issued | FREDDIE RIVERA |
| Interior/Exterior Lathing | 10/31/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/3/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/14/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 12/14/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 12/14/2022 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 12/14/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 12/14/2022 | Approved | ALIZAH MAYAGOITIA |
| MERV13>=Rough | 12/14/2022 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 12/14/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 3/10/2023 | Approved | FREDDIE RIVERA |
| Final | 3/10/2023 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 3/10/2023 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 3/10/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 4/11/2023 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/11/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 4/25/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 4/25/2023 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 4/25/2023 | Partial Inspection | FREDDIE RIVERA |
| Final | 5/2/2023 | Partial Inspection | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 5/2/2023 | SGSOV Approved | FREDDIE RIVERA |
| Final | 5/10/2023 | Conditional Approval | FREDDIE RIVERA |
| Final | 5/15/2023 | Corrections Issued | FREDDIE RIVERA |