1123 S CRENSHAW BLVD 90019

Certificate Information: 1123 S CRENSHAW BLVD 90019

Application / Permit
20016-10000-21350
Plan Check / Job No.
B20LA15668
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
TENANT IMPROVEMENT FOR DINE-IN RESTAURANT WITH OUTDOOR PATIO AND NEW RETAIL SPACE
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/25/2020 SERGIO GUTIERREZ
Corrections Issued 10/16/2020 SERGIO GUTIERREZ
Quality Review Completed 10/22/2020 KESETE HAREGOT
Building Plans Picked Up 10/22/2020 APPLICANT
Applicant returned to address corrections 5/26/2021 SERGIO GUTIERREZ
Plan Check Approved 6/3/2021 SERGIO GUTIERREZ
Issued 9/1/2021 APPLICANT
Permit Finaled 4/13/2026 ERNESTO CORRAL
CofO Issued 4/13/2026 ERNESTO CORRAL
Permit Finaled 4/13/2026 ERNESTO CORRAL

Permit Application Clearance Information

Miscellaneous Cleared 12/1/2020 ANACANY HURTADO
ZA Case Cleared 12/1/2020 ANACANY HURTADO
ZA Case Cleared 12/1/2020 ANACANY HURTADO
Miscellaneous Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
ZA Case Cleared 12/10/2020 ANACANY HURTADO
Eng Process Fee Ord 176,300 Cleared 3/2/2021 CECILIO NAVARRO
DAS Clearance Cleared 3/11/2021 SERGIO GUTIERREZ
Sewer availability Cleared 5/6/2021 CECILIO NAVARRO

Contact Information

Contractor A Plus Building Techs Inc; Lic. No.: 1020765-B 3041 CALANDA AVE      ALTADENA, CA 91001

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 11/5/2021 Partial Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/9/2021 Partial Approval KATY RAMIREZ
T-Bar Ceiling 5/16/2022 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 7/7/2022 Approved EDWIN GREGORYONA
T-Bar Ceiling 8/25/2022 Partial Inspection KATY RAMIREZ
Final 8/18/2023 Not Ready for Inspection JEROME BLACKWOOD
METHANE-Final 8/18/2023 Approved JEROME BLACKWOOD
METHANE-Rough 8/18/2023 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 8/18/2023 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 8/18/2023 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 8/18/2023 Approved JEROME BLACKWOOD
Final 10/31/2023 Corrections Issued ALFREDO LOPEZ
Smoke Detectors 10/31/2023 Not Ready for Inspection ALFREDO LOPEZ
Final 4/16/2024 Partial Approval MARTIN TAVITIAN
Smoke Detectors 4/16/2024 Approved MARTIN TAVITIAN