1141 S ALVIRA ST 90035

Certificate Information: 1141 S ALVIRA ST 90035

Application / Permit
20016-10000-21339
Plan Check / Job No.
B20LA15654
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* CONVERSION OF (E) GARAGE & STORAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 7/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 LAMAR DAVIS
Corrections Issued 9/30/2020 LAMAR DAVIS
Quality Review Completed 10/13/2020 TU HUA
Applicant returned to address corrections 1/8/2021 LAMAR DAVIS
Applicant returned to address corrections 1/15/2021 LAMAR DAVIS
Plan Check Approved 1/28/2021 LAMAR DAVIS
Issued 2/18/2021 APPLICANT
CofO in Progress 5/13/2022 JOSE AVILA
Permit Finaled 7/29/2022 DEROLD HAUFF
CofO Issued 7/29/2022 DEROLD HAUFF
Permit Finaled 7/29/2022 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 10/13/2020 MIGUEL GAMBOA
Address approval Cleared 10/16/2020 RENZ SORIANO
Sewer availability Cleared 10/16/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/19/2020 RENZ SORIANO
HPOZ Cleared 12/18/2020 JONATHAN KAPLAN
Construction within easement Cleared 12/29/2020 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/26/2021 Not Ready for Inspection STUART CHAPMAN
Pre-Inspection 3/31/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 4/22/2021 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 4/22/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 5/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Rough 5/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
METHANE-Rough 5/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/12/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/14/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 5/14/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 5/14/2021 Not Ready for Inspection STUART CHAPMAN
METHANE-Rough 5/14/2021 Approved STUART CHAPMAN
PLUMBING-Rough 5/14/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Rough 5/19/2021 Approved STUART CHAPMAN
HVAC-Rough 5/19/2021 Approved STUART CHAPMAN
PLUMBING-Rough 5/19/2021 Approved STUART CHAPMAN
Insulation 5/27/2021 Not Ready for Inspection WILLIAM WREN
Interior/Exterior Lathing 5/27/2021 Not Ready for Inspection WILLIAM WREN
Floor/Roof Diaphrgm/Shear Wall 6/1/2021 Partial Approval RUBEN SALAS
BUILDING-Rough-Frame 6/10/2021 Approved CALEB MEISTER
Drywall Nailing 6/10/2021 Approved CALEB MEISTER
Insulation 6/10/2021 Approved CALEB MEISTER
Interior/Exterior Lathing 6/10/2021 Approved CALEB MEISTER
Underground Mechanical 6/28/2021 Partial Approval SCOTT FINNILA
ELECTRICAL-Final 8/31/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Final 9/1/2021 Corrections Issued SCOTT FINNILA
Final 9/1/2021 Corrections Issued SCOTT FINNILA
HVAC-Final 9/1/2021 Corrections Issued SCOTT FINNILA
PLUMBING-Final 9/1/2021 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 3/24/2022 Approved JOSE AVILA
Final 3/24/2022 Corrections Issued JOSE AVILA
Green Building Final 3/24/2022 Approved JOSE AVILA
Green Building Rough 3/24/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 3/24/2022 Approved JOSE AVILA
Final 4/14/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Final 5/11/2022 Approved JOSE AVILA
Final 5/13/2022 OK to Issue CofO JOSE AVILA