1901 W 7TH ST 90057

Certificate Information: 1901 W 7TH ST 90057

Application / Permit
20016-10000-21308
Plan Check / Job No.
B20LA15642
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Community Center operated by philanthropic organization
Work Description
Change of use from Retail to Cultural Center, including Tenant improvement to entire space
Permit Issued
Issued on 12/16/2020
Issuing Office
Current Status
CofO Issued on 12/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/1/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 HERNAN ARREOLA
Disabled Access Plans Picked Up 9/11/2020 APPLICANT
Corrections Issued 9/28/2020 HERNAN ARREOLA
Quality Review Completed 10/2/2020 ALLEN MANALANSAN
Building Plans Picked Up 10/6/2020 APPLICANT
Applicant returned to address corrections 11/5/2020 HERNAN ARREOLA
Green Plans Picked Up 11/10/2020 APPLICANT
Applicant returned to address corrections 12/15/2020 HERNAN ARREOLA
Plan Check Approved 12/16/2020 HERNAN ARREOLA
Issued 12/16/2020 APPLICANT
CofO in Progress 12/21/2021 NICK DANERI
CofO Issued 12/21/2021 ERNESTO CORRAL
Permit Finaled 12/21/2021 ERNESTO CORRAL

Permit Application Clearance Information

Sewer availability Cleared 10/8/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/9/2020 WALLIE JONG
Green Code Cleared 11/7/2020 AARON COSTA
ZA Case Cleared 11/10/2020 DANG NGUYEN
ZA Case Cleared 11/10/2020 DANG NGUYEN
Redevelopment Project Area Cleared 11/12/2020 DAVID URITA
Fire Marshall Fire Life Safety Cleared 11/27/2020 ANDREW KO
DAS Clearance Cleared 12/8/2020 SHINE LIN

Contact Information

Contractor Howard Building Corporation; Lic. No.: 445804-B 707 WILSHIRE BLVD STE 3750      LOS ANGELES, CA 90017
Engineer Ibarra,, Marco Antonio; Lic. No.: C74010 16 N MARENGON AVE STE 604      PASADENA, CA 91101

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 2/18/2021 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 2/25/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 3/4/2021 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 3/10/2021 Conditional Approval DANIEL COLLINS
Footing/Foundation/Slab 3/11/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 3/15/2021 Conditional Approval DANIEL COLLINS
Drywall Nailing 3/24/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 3/30/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 4/7/2021 Corrections Issued DANIEL COLLINS
Wood Frame 4/12/2021 Corrections Issued DANIEL COLLINS
Deputy Drilled-In Anchors 4/23/2021 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 4/26/2021 Approved DANIEL COLLINS
Deputy EIFS 4/27/2021 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 4/29/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 5/7/2021 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 5/11/2021 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 5/19/2021 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 5/21/2021 Conditional Approval NICK DANERI
Deputy Steel/Welding 5/25/2021 Conditional Approval DANIEL COLLINS
Structural Steel Frame 5/27/2021 Approved DANIEL COLLINS
Deputy Drilled-In Anchors 9/7/2021 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 9/8/2021 Conditional Approval DANIEL COLLINS
Final 9/14/2021 Conditional Approval DANIEL COLLINS
Green Building Final 9/14/2021 Approved DANIEL COLLINS
Green Building Rough 9/14/2021 Approved DANIEL COLLINS
Reinforced Concrete Frame 9/14/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Approved DANIEL COLLINS
Smoke Detectors 9/14/2021 Approved DANIEL COLLINS
Final 12/13/2021 Conditional Approval NICK DANERI