701 1/2 W 42ND ST 90037
Certificate Information: 701 1/2 W 42ND ST 90037
- Application / Permit
- 20016-10000-21277
- Plan Check / Job No.
- B20LA15626
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert existing detached one-car garage to an Accessory Dwelling Unit (ADU)
- Permit Issued
- Issued on 3/18/2021
- Issuing Office
- Current Status
- CofO Issued on 1/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/29/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 9/28/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/7/2020 | MINYE PAK |
| Applicant returned to address corrections | 12/5/2020 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 1/25/2021 | ARSALAN SHABESTARI |
| Applicant returned to address corrections | 3/2/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 3/10/2021 | ARSALAN SHABESTARI |
| Issued | 3/18/2021 | APPLICANT |
| CofO in Progress | 12/15/2021 | SABAS ALONSO |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
| CofO Issued | 1/6/2022 | DEROLD HAUFF |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2020 | JAMES KHO |
| Sewer availability | Cleared | 10/20/2020 | JAMES KHO |
| Eng Process Fee Ord 176,300 | Cleared | 10/23/2020 | JAMES KHO |
| Construction near power lines | Cleared | 3/7/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/7/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/21/2021 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/7/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| Footing/Foundation/Slab | 5/7/2021 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 5/7/2021 | Not Ready for Inspection | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 5/21/2021 | Corrections Issued | SCOTT FINNILA |
| ELECTRICAL-Rough | 5/21/2021 | No Access for Inspection | SCOTT FINNILA |
| HVAC-Rough | 5/21/2021 | Corrections Issued | SCOTT FINNILA |
| PLUMBING-Rough | 5/21/2021 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 6/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Green Building Rough | 6/9/2021 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 6/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/16/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 6/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 6/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 6/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/23/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 6/24/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Pre-Inspection | 6/24/2021 | Partial Inspection | JESUS PINEDA |
| Drywall Nailing | 6/30/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/7/2021 | No Access for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 7/19/2021 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 7/20/2021 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Rough-Elec/Plmb/HVAC | 7/20/2021 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Rough | 7/27/2021 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 9/9/2021 | Approved | SABAS ALONSO |
| Final | 9/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 9/9/2021 | Approved | SABAS ALONSO |
| Green Building Rough | 9/9/2021 | Approved | SABAS ALONSO |
| Smoke Detectors | 9/9/2021 | Not Ready for Inspection | SABAS ALONSO |
| Drywall Nailing | 9/14/2021 | Approved | SABAS ALONSO |
| Insulation | 9/14/2021 | Approved | SABAS ALONSO |
| Service/Power Release | 10/21/2021 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/29/2021 | Corrections Issued | SABAS ALONSO |
| Smoke Detectors | 11/29/2021 | Approved | SABAS ALONSO |
| Final | 12/10/2021 | OK to Issue CofO | SABAS ALONSO |