237 E 68TH ST 90003

Certificate Information: 237 E 68TH ST 90003

Application / Permit
20016-10000-21276
Plan Check / Job No.
B20LA15625
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN CHECK* (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)-(d)
Permit Issued
Issued on 11/16/2020
Issuing Office
Metro
Current Status
CofO Issued on 9/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 LAMAR DAVIS
Corrections Issued 9/29/2020 LAMAR DAVIS
Quality Review Completed 10/20/2020 TU HUA
Applicant returned to address corrections 10/20/2020 LAMAR DAVIS
Applicant returned to address corrections 10/29/2020 LAMAR DAVIS
Plan Check Approved 11/5/2020 LAMAR DAVIS
Issued 11/16/2020 APPLICANT
CofO in Progress 9/10/2021 HORACE FULTZ
Permit Finaled 9/20/2021 DEROLD HAUFF
CofO Issued 9/20/2021 DEROLD HAUFF
Permit Finaled 9/20/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/7/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/7/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/7/2020 CECILIO NAVARRO
Sewer availability Cleared 10/7/2020 CECILIO NAVARRO

Contact Information

Contractor Owner-Builder       ,
Engineer Mayer,, Robert; Lic. No.: S1991 5109 BELLAIRE AVENUE      N HOLLYWOOD, CA 91607

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/1/2020 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 12/10/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 12/24/2020 Corrections Issued EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 12/30/2020 Not Ready for Inspection JOSEPH MCGARRY
Underground Mechanical 12/30/2020 Partial Approval JOSEPH MCGARRY
Pre-Inspection 1/11/2021 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 1/20/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 2/9/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 2/9/2021 Not Ready for Inspection FREDDIE RIVERA
Verify Sprinkler Sign Off 2/9/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 2/17/2021 Partial Approval FREDDIE RIVERA
Green Building Rough 2/17/2021 Corrections Issued FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 3/1/2021 Corrections Issued DAVID FEILER
PLUMBING-Rough 3/1/2021 Not Ready for Inspection DAVID FEILER
Drywall Nailing 3/9/2021 Not Ready for Inspection DAVID FEILER
Green Building Rough 3/9/2021 Not Ready for Inspection DAVID FEILER
Deputy Wood Construction 3/12/2021 No Access for Inspection ELMER BLAND
Interior/Exterior Lathing 3/17/2021 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 3/24/2021 Conditional Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/24/2021 Approved EUGENE CASSIDY
Green Building Rough 3/24/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 3/24/2021 Approved EUGENE CASSIDY
Insulation 3/30/2021 Conditional Approval DAVID FEILER
Drywall Nailing 4/19/2021 Approved SABAS ALONSO
ELECTRICAL-Final 6/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 6/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 6/3/2021 Not Ready for Inspection ALEJANDRO DE ARTOLA
HVAC-Final 6/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 6/3/2021 SGSOV Not Ready ALEJANDRO DE ARTOLA
Smoke Detectors 6/3/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 9/9/2021 Approved SABAS ALONSO
Final 9/9/2021 OK to Issue CofO SABAS ALONSO
Green Building Final 9/9/2021 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/9/2021 SGSOV Approved SABAS ALONSO
Service/Power Release 9/9/2021 Approved SABAS ALONSO
Smoke Detectors 9/9/2021 Approved SABAS ALONSO