5249 1/2-1/4 E MERIDIAN ST 90042
Certificate Information: 5249 1/2-1/4 E MERIDIAN ST 90042
- Application / Permit
- 20016-10000-21216
- Plan Check / Job No.
- B20LA15593
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan - CONVERT EXISTING GARAGE INTO ADU
- Permit Issued
- Issued on 12/2/2020
- Issuing Office
- Current Status
- CofO Issued on 3/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/31/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2020 | ARSALAN SHABESTARI |
| Corrections Issued | 9/28/2020 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/13/2020 | PRANITA SHAH |
| Applicant returned to address corrections | 11/10/2020 | ARSALAN SHABESTARI |
| Plan Check Approved | 11/19/2020 | ARSALAN SHABESTARI |
| Issued | 12/2/2020 | APPLICANT |
| CofO in Progress | 3/5/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
| CofO Issued | 3/9/2025 | DEROLD HAUFF |
| Permit Finaled | 3/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2020 | THOMAS LANG |
| Sewer availability | Cleared | 10/14/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2020 | PAMELA TENEZA |
Contact Information
| Contractor | J & L Construction And Investments Inc; Lic. No.: 1028412-B | 10750 REDMONT AVE TUJUNGA, CA 91042 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/26/2022 | Approved | CRAIG VAUGHAN |
| Pre-Inspection | 7/18/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 6/20/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/10/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/10/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 10/16/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 11/12/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 11/12/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/12/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/18/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/18/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 11/18/2024 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 11/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Wood Frame | 11/22/2024 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 11/27/2024 | Not Ready for Inspection | ANTHONY RAMOS |
| Interior/Exterior Lathing | 11/27/2024 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 12/2/2024 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 1/16/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/16/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 1/16/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 1/16/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 1/16/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 1/16/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 1/16/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 1/17/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 1/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 1/17/2025 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 1/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Deputy Drilled-In Anchors | 2/3/2025 | Conditional Approval | CRAIG DAVIS |
| Wood Frame | 2/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/4/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 3/5/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |