5249 1/2-1/4 E MERIDIAN ST 90042

Certificate Information: 5249 1/2-1/4 E MERIDIAN ST 90042

Application / Permit
20016-10000-21216
Plan Check / Job No.
B20LA15593
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan - CONVERT EXISTING GARAGE INTO ADU
Permit Issued
Issued on 12/2/2020
Issuing Office
Current Status
CofO Issued on 3/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 ARSALAN SHABESTARI
Corrections Issued 9/28/2020 ARSALAN SHABESTARI
Quality Review Completed 10/13/2020 PRANITA SHAH
Applicant returned to address corrections 11/10/2020 ARSALAN SHABESTARI
Plan Check Approved 11/19/2020 ARSALAN SHABESTARI
Issued 12/2/2020 APPLICANT
CofO in Progress 3/5/2025 ALIZAH MAYAGOITIA
Permit Finaled 3/9/2025 DEROLD HAUFF
CofO Issued 3/9/2025 DEROLD HAUFF
Permit Finaled 3/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/14/2020 THOMAS LANG
Sewer availability Cleared 10/14/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/15/2020 PAMELA TENEZA

Contact Information

Contractor J & L Construction And Investments Inc; Lic. No.: 1028412-B 10750 REDMONT AVE      TUJUNGA, CA 91042

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/26/2022 Approved CRAIG VAUGHAN
Pre-Inspection 7/18/2022 Not Ready for Inspection CRAIG VAUGHAN
Pre-Inspection 6/20/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval ALIZAH MAYAGOITIA
Drywall Nailing 10/10/2024 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/10/2024 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/16/2024 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 11/12/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 11/12/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 11/12/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/18/2024 Partial Approval ALIZAH MAYAGOITIA
Green Building Rough 11/18/2024 Approved ALIZAH MAYAGOITIA
Wood Frame 11/18/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 11/22/2024 Approved ALIZAH MAYAGOITIA
Insulation 11/22/2024 Approved ALIZAH MAYAGOITIA
Wood Frame 11/22/2024 Approved ALIZAH MAYAGOITIA
Drywall Nailing 11/27/2024 Not Ready for Inspection ANTHONY RAMOS
Interior/Exterior Lathing 11/27/2024 Approved ANTHONY RAMOS
Drywall Nailing 12/2/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 1/16/2025 Approved ALIZAH MAYAGOITIA
Final 1/16/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 1/16/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 1/16/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Final 1/16/2025 Corrections Issued ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 1/16/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 1/16/2025 Approved ALIZAH MAYAGOITIA
Final 1/17/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 1/17/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 1/17/2025 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 1/30/2025 Approved ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 2/3/2025 Conditional Approval CRAIG DAVIS
Wood Frame 2/5/2025 Approved ALIZAH MAYAGOITIA
Final 3/4/2025 Conditional Approval ALIZAH MAYAGOITIA
Final 3/5/2025 OK to Issue CofO ALIZAH MAYAGOITIA