808 N CRESTHAVEN DR 90042

Certificate Information: 808 N CRESTHAVEN DR 90042

Application / Permit
20016-10000-21214
Plan Check / Job No.
B20LA15591
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePLAN* CONVERSION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
CofO Corrected on 9/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 LAMAR DAVIS
Corrections Issued 9/30/2020 LAMAR DAVIS
Quality Review Completed 10/15/2020 TU HUA
Applicant returned to address corrections 10/30/2020 LAMAR DAVIS
Applicant returned to address corrections 11/5/2020 LAMAR DAVIS
Plan Check Approved 11/16/2020 LAMAR DAVIS
Issued 11/19/2020 APPLICANT
CofO in Progress 5/12/2022 AMY COLIN
CofO Issued-Status Void 5/20/2022 DEROLD HAUFF
Permit Finaled-Status Void 5/20/2022 DEROLD HAUFF
Re-Activate Permit 9/21/2023 DEROLD HAUFF
Permit Finaled 9/26/2023 DEROLD HAUFF
CofO Corrected 9/26/2023 DEROLD HAUFF
Permit Finaled 9/26/2023 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 10/19/2020 KATIE DEBIASE
Grading Pre-Inspection Cleared 10/22/2020 BRIAN MILLER
Address approval Cleared 10/26/2020 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/26/2020 WALLIE JONG
Sewer availability Cleared 10/26/2020 WALLIE JONG

Contact Information

Contractor J & L Construction And Investments Inc; Lic. No.: 1028412-B 10750 REDMONT AVE      TUJUNGA, CA 91042

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/11/2020 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 5/25/2021 Approved COREY HUPP
ELECTRICAL-Rough 11/3/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 11/3/2021 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/5/2021 Corrections Issued COREY HUPP
Excavation/Setback/Form/Re-Bar 11/10/2021 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 11/10/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 12/9/2021 Approved OSVALDO PARAMO
HVAC-Rough 12/9/2021 Approved OSVALDO PARAMO
PLUMBING-Rough 12/9/2021 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 5/11/2022 Approved AMY COLIN
Final 5/11/2022 Partial Inspection AMY COLIN
Green Building Final 5/11/2022 Approved AMY COLIN
Green Building Rough 5/11/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 5/11/2022 SGSOV Approved AMY COLIN
Smoke Detectors 5/11/2022 Approved AMY COLIN
ELECTRICAL-Final 5/12/2022 Approved AMY COLIN
Final 5/12/2022 OK to Issue CofO AMY COLIN
HVAC-Final 5/12/2022 Approved AMY COLIN
PLUMBING-Final 5/12/2022 Approved AMY COLIN