535 S GAYLEY AVE 90024

Certificate Information: 535 S GAYLEY AVE 90024

Application / Permit
20016-10000-21191
Plan Check / Job No.
B20LA15579
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
eplan. Renovation of Existing Fitness Center Building at Ariel Court Apartments, including exterior opening modification, demolition and construction of new interior partitions, and finishes.
Permit Issued
Issued on 2/26/2021
Issuing Office
Current Status
Permit Finaled on 7/29/2021

Permit Application Status History

Submitted 8/31/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 MONICA RAMIREZ
Corrections Issued 9/3/2020 MONICA RAMIREZ
Applicant returned to address corrections 9/22/2020 MONICA RAMIREZ
Applicant returned to address corrections 9/24/2020 HELEN NGUYEN
Applicant returned to address corrections 10/1/2020 MONICA RAMIREZ
Applicant returned to address corrections 10/12/2020 MICHAEL LOPEZ
Applicant returned to address corrections 12/4/2020 LAMAR DAVIS
Plan Check Approved 2/20/2021 LAMAR DAVIS
Issued 2/26/2021 APPLICANT
Permit Finaled 7/27/2021 PAUL DAVIDSON

Permit Application Clearance Information

"Q" conditions Cleared 10/5/2020 DYLAN SITTIG
Specific Plan Cleared 10/5/2020 DYLAN SITTIG
Tenant Habitability Plan Cleared 12/9/2020 ISMAEL HERNANDEZ

Contact Information

Architect Holland,, Scott Charles; Lic. No.: C23872 P.O. BOX 301      CORONA DEL MAR, CA 92625
Contractor Ray Hart General Contractor; Lic. No.: 647755-B 250 EAST 16TH STREET #C      COSTA MESA, CA 92627

Inspector Information

ROGELIO REYNA, (310) 914-3920 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/5/2021 No Access for Inspection PAUL DAVIDSON
Pre-Inspection 4/13/2021 Approved PAUL DAVIDSON
Wood Frame 4/13/2021 Conditional Approval PAUL DAVIDSON
Insulation 4/30/2021 Approved PAUL DAVIDSON
Drywall Nailing 5/20/2021 Approved PAUL DAVIDSON
Interior/Exterior Lathing 5/20/2021 Approved PAUL DAVIDSON
Special/Order Compliance 5/26/2021 No Access for Inspection PAUL DAVIDSON
Final 7/1/2021 Not Ready for Inspection PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 7/1/2021 SGSOV Not Ready PAUL DAVIDSON
Smoke Detectors 7/1/2021 Not Ready for Inspection PAUL DAVIDSON
Final 7/27/2021 Permit Finaled PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 7/27/2021 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 7/27/2021 Approved PAUL DAVIDSON