17335 W TOQUET DR 91316
Certificate Information: 17335 W TOQUET DR 91316
- Application / Permit
- 20016-10000-21125
- Plan Check / Job No.
- B20LA15536
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO AND REMODALE TO (E) SINGLE FAMILY DWELING
- Permit Issued
- Issued on 1/29/2021
- Issuing Office
- Current Status
- CofO Issued on 1/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/29/2020 | RACHEL BEYENE |
| Corrections Issued | 10/1/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 10/28/2020 | TSE MING HUANG |
| Applicant returned to address corrections | 12/9/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 12/11/2020 | RACHEL BEYENE |
| Plan Check Approved | 1/19/2021 | DANIEL YIP |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Issued | 1/29/2021 | APPLICANT |
| CofO in Progress | 8/7/2023 | VINCENT HANLEY |
| Permit Finaled | 1/17/2024 | JOHN JANSON |
| CofO Issued | 1/17/2024 | JOHN JANSON |
| Permit Finaled | 1/17/2024 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 10/21/2020 | JOHN TRIANTAFYLLOS |
| Low Impact Development | Cleared | 11/20/2020 | ORVAL HERNANDEZ-MARCI |
| Grading Pre-Inspection | Cleared | 1/13/2021 | RAHEL BEYENE |
| Roof/Waste drainage to street | Cleared | 1/15/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/2/2021 | Approved | RONALD COWAN |
| ELECTRICAL-Rough | 3/19/2021 | Approved | RONALD COWAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2021 | Partial Approval | RONALD COWAN |
| PLUMBING-Rough | 3/19/2021 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | RONALD COWAN |
| Green Building Rough | 4/7/2021 | Approved | RONALD COWAN |
| Drywall Nailing | 4/15/2021 | Approved | RONALD COWAN |
| Insulation | 4/15/2021 | Approved | RONALD COWAN |
| Final | 4/28/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 4/28/2023 | Approved | VINCENT HANLEY |
| Smoke Detectors | 4/28/2023 | Approved | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 5/8/2023 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/8/2023 | Approved | VINCENT HANLEY |
| Final | 5/8/2023 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 5/8/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 5/8/2023 | Approved | VINCENT HANLEY |
| Final | 8/7/2023 | OK to Issue CofO | VINCENT HANLEY |