17335 W TOQUET DR 91316

Certificate Information: 17335 W TOQUET DR 91316

Application / Permit
20016-10000-21125
Plan Check / Job No.
B20LA15536
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND REMODALE TO (E) SINGLE FAMILY DWELING
Permit Issued
Issued on 1/29/2021
Issuing Office
Current Status
CofO Issued on 1/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/28/2020 APPLICANT
Assigned to Plan Check Engineer 8/29/2020 RACHEL BEYENE
Corrections Issued 10/1/2020 RACHEL BEYENE
Applicant returned to address corrections 10/28/2020 TSE MING HUANG
Applicant returned to address corrections 12/9/2020 RACHEL BEYENE
Applicant returned to address corrections 12/11/2020 RACHEL BEYENE
Plan Check Approved 1/19/2021 DANIEL YIP
Building Plans Picked Up 1/21/2021 APPLICANT
Issued 1/29/2021 APPLICANT
CofO in Progress 8/7/2023 VINCENT HANLEY
Permit Finaled 1/17/2024 JOHN JANSON
CofO Issued 1/17/2024 JOHN JANSON
Permit Finaled 1/17/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/21/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 10/21/2020 JOHN TRIANTAFYLLOS
Low Impact Development Cleared 11/20/2020 ORVAL HERNANDEZ-MARCI
Grading Pre-Inspection Cleared 1/13/2021 RAHEL BEYENE
Roof/Waste drainage to street Cleared 1/15/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2021 Approved RONALD COWAN
ELECTRICAL-Rough 3/19/2021 Approved RONALD COWAN
Floor/Roof Diaphrgm/Shear Wall 3/19/2021 Partial Approval RONALD COWAN
PLUMBING-Rough 3/19/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 4/7/2021 Approved RONALD COWAN
Green Building Rough 4/7/2021 Approved RONALD COWAN
Drywall Nailing 4/15/2021 Approved RONALD COWAN
Insulation 4/15/2021 Approved RONALD COWAN
Final 4/28/2023 Corrections Issued VINCENT HANLEY
Green Building Final 4/28/2023 Approved VINCENT HANLEY
Smoke Detectors 4/28/2023 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 5/8/2023 Approved VINCENT HANLEY
ELECTRICAL-Final 5/8/2023 Approved VINCENT HANLEY
Final 5/8/2023 Corrections Issued VINCENT HANLEY
HVAC-Final 5/8/2023 Approved VINCENT HANLEY
PLUMBING-Final 5/8/2023 Approved VINCENT HANLEY
Final 8/7/2023 OK to Issue CofO VINCENT HANLEY