14823 W GREENLEAF ST 91403
Certificate Information: 14823 W GREENLEAF ST 91403
- Application / Permit
- 20016-10000-21045
- Plan Check / Job No.
- B20LA15446
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | KEVIN MORALES |
| Corrections Issued | 9/30/2020 | KEVIN MORALES |
| Quality Review Completed | 10/6/2020 | EUGENE BARBEAU |
| Applicant returned to address corrections | 10/20/2020 | KEVIN MORALES |
| Plan Check Approved | 10/22/2020 | KEVIN MORALES |
| Issued | 10/23/2020 | APPLICANT |
| CofO in Progress | 4/28/2021 | CHARLES POWELL |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 10/14/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Build Method Construction Inc; Lic. No.: 1059684-B | 12117 VALLEYHEART DRIVE SUITE 305 STUDIO CITY, CA 91604 |
| Engineer | Xiao,, Qiang; Lic. No.: S5289 | 1520 BROOKHOLLOW #45 SANTA ANA, CA 92705 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/29/2020 | Corrections Issued | CHARLES POWELL |
| PLUMBING-Rough | 10/29/2020 | Corrections Issued | CHARLES POWELL |
| Footing/Foundation/Slab | 11/4/2020 | Partial Approval | CHARLES POWELL |
| PLUMBING-Rough | 11/4/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 11/17/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 11/17/2020 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 11/17/2020 | Corrections Issued | CHARLES POWELL |
| Rough-Elec/Plmb/HVAC | 11/17/2020 | Corrections Issued | CHARLES POWELL |
| Wood Frame | 11/17/2020 | Not Ready for Inspection | CHARLES POWELL |
| ELECTRICAL-Rough | 11/23/2020 | Partial Approval | CHARLES POWELL |
| Footing/Foundation/Slab | 11/23/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 11/23/2020 | Approved | CHARLES POWELL |
| Shower Pan | 11/23/2020 | Approved | CHARLES POWELL |
| Insulation | 12/1/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 12/10/2020 | Not Ready for Inspection | CHARLES POWELL |
| Drywall Nailing | 12/15/2020 | Approved | CHARLES POWELL |
| Sewer | 1/12/2021 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 1/20/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 2/19/2021 | Approved | CHARLES POWELL |
| Final | 2/19/2021 | Corrections Issued | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 2/19/2021 | SGSOV Approved | CHARLES POWELL |
| Smoke Detectors | 2/19/2021 | Not Ready for Inspection | CHARLES POWELL |
| Final | 3/2/2021 | Corrections Issued | CHARLES POWELL |
| Smoke Detectors | 3/2/2021 | Not Ready for Inspection | CHARLES POWELL |
| Final | 3/8/2021 | Corrections Issued | CHARLES POWELL |
| Smoke Detectors | 3/8/2021 | Approved | CHARLES POWELL |
| Final | 4/5/2021 | Partial Approval | CHARLES POWELL |
| Final | 4/14/2021 | Not Ready for Inspection | CHARLES POWELL |
| Final | 4/27/2021 | OK to Issue CofO | CHARLES POWELL |