14823 W GREENLEAF ST 91403

Certificate Information: 14823 W GREENLEAF ST 91403

Application / Permit
20016-10000-21045
Plan Check / Job No.
B20LA15446
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 10/23/2020
Issuing Office
Current Status
CofO Issued on 6/5/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 KEVIN MORALES
Corrections Issued 9/30/2020 KEVIN MORALES
Quality Review Completed 10/6/2020 EUGENE BARBEAU
Applicant returned to address corrections 10/20/2020 KEVIN MORALES
Plan Check Approved 10/22/2020 KEVIN MORALES
Issued 10/23/2020 APPLICANT
CofO in Progress 4/28/2021 CHARLES POWELL
CofO Issued 6/5/2021 MICHAEL SMITH
Permit Finaled 6/5/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/14/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/14/2020 ADRIAN CASTRO
Sewer availability Cleared 10/14/2020 ADRIAN CASTRO

Contact Information

Contractor Build Method Construction Inc; Lic. No.: 1059684-B 12117 VALLEYHEART DRIVE   SUITE 305    STUDIO CITY, CA 91604
Engineer Xiao,, Qiang; Lic. No.: S5289 1520 BROOKHOLLOW #45      SANTA ANA, CA 92705

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/29/2020 Corrections Issued CHARLES POWELL
PLUMBING-Rough 10/29/2020 Corrections Issued CHARLES POWELL
Footing/Foundation/Slab 11/4/2020 Partial Approval CHARLES POWELL
PLUMBING-Rough 11/4/2020 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 11/17/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 11/17/2020 Not Ready for Inspection CHARLES POWELL
PLUMBING-Rough 11/17/2020 Corrections Issued CHARLES POWELL
Rough-Elec/Plmb/HVAC 11/17/2020 Corrections Issued CHARLES POWELL
Wood Frame 11/17/2020 Not Ready for Inspection CHARLES POWELL
ELECTRICAL-Rough 11/23/2020 Partial Approval CHARLES POWELL
Footing/Foundation/Slab 11/23/2020 Approved CHARLES POWELL
Interior/Exterior Lathing 11/23/2020 Approved CHARLES POWELL
Shower Pan 11/23/2020 Approved CHARLES POWELL
Insulation 12/1/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 12/4/2020 Approved CHARLES POWELL
Drywall Nailing 12/10/2020 Not Ready for Inspection CHARLES POWELL
Drywall Nailing 12/15/2020 Approved CHARLES POWELL
Sewer 1/12/2021 Corrections Issued ARAM AVEDISIAN
Sewer 1/20/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 2/19/2021 Approved CHARLES POWELL
Final 2/19/2021 Corrections Issued CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 2/19/2021 SGSOV Approved CHARLES POWELL
Smoke Detectors 2/19/2021 Not Ready for Inspection CHARLES POWELL
Final 3/2/2021 Corrections Issued CHARLES POWELL
Smoke Detectors 3/2/2021 Not Ready for Inspection CHARLES POWELL
Final 3/8/2021 Corrections Issued CHARLES POWELL
Smoke Detectors 3/8/2021 Approved CHARLES POWELL
Final 4/5/2021 Partial Approval CHARLES POWELL
Final 4/14/2021 Not Ready for Inspection CHARLES POWELL
Final 4/27/2021 OK to Issue CofO CHARLES POWELL