13530 W VICTORY BLVD 91401
Certificate Information: 13530 W VICTORY BLVD 91401
- Application / Permit
- 20016-10000-20973
- Plan Check / Job No.
- B20LA15397
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CH. 93 USING WOOD SHEAR WALL
- Permit Issued
- Issued on 10/14/2020
- Issuing Office
- Current Status
- CofC Issued on 2/18/2021
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | HANS SANTIAGO |
| Plan Check Approved | 9/4/2020 | ANDREW SANTIAGO |
| Issued | 10/14/2020 | APPLICANT |
| OK for CofC | 1/15/2021 | JOE VELASQUEZ |
| CofC Issued | 2/18/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/18/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Retrofit 1; Lic. No.: 1003868-B | 19326 VENTURA BLVD STE 200 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/27/2020 | Partial Inspection | JONATHAN QUACH |
| Wall Anchors | 11/20/2020 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 11/20/2020 | Partial Approval | JOE VELASQUEZ |
| Insulation | 11/24/2020 | Partial Approval | JOE VELASQUEZ |
| Deputy Steel/Welding | 12/8/2020 | No Access for Inspection | JOE VELASQUEZ |
| Wood Frame | 12/18/2020 | Approved | JOE VELASQUEZ |
| Insulation | 12/30/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 12/31/2020 | Approved | DANIEL VARNUM |
| Final | 1/15/2021 | OK for CofC | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Approved | JOE VELASQUEZ |
| Smoke Detectors | 1/15/2021 | Approved | JOE VELASQUEZ |