4225 S NORTON AVE 90008
Certificate Information: 4225 S NORTON AVE 90008
- Application / Permit
- 20016-10000-20939
- Plan Check / Job No.
- B20LA15388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (e) GARAGE INTO ADU PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 2/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2020 | LUKE GONZALES |
| Corrections Issued | 8/28/2020 | LUKE GONZALES |
| Plan Check Approved | 9/9/2021 | GEORGE ALVAREZ |
| Issued | 9/27/2021 | APPLICANT |
| Building Plans Picked Up | 9/29/2021 | APPLICANT |
| CofO in Progress | 12/28/2022 | ANTHONY EGSON |
| No Progress | 2/11/2023 | RICHARD STEINBACH |
| CofO in Progress | 2/14/2023 | RONALD MYRICK |
| Permit Finaled | 2/14/2023 | RONALD MYRICK |
| CofO Issued | 2/14/2023 | RONALD MYRICK |
| Permit Finaled | 2/14/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2020 | JEANIE LAM |
| Sewer availability | Cleared | 11/17/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/18/2020 | JEANIE LAM |
| Construction within easement | Cleared | 6/21/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yassin,, Diaa Aldin; Lic. No.: C56295 | 2207 MERCED AVE SOUTH EL MONTE, CA 91733 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/1/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/21/2022 | Corrections Issued | ANTHONY EGSON |
| Sewer | 3/22/2022 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 3/30/2022 | Corrections Issued | ANTHONY EGSON |
| Footing/Foundation/Slab | 4/5/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 4/22/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 5/26/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 6/9/2022 | Approved | ANTHONY EGSON |
| Insulation | 6/29/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 7/20/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/3/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 8/3/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 11/3/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 11/3/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 11/3/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 11/3/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/3/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/3/2022 | SGSOV Not Ready | ANTHONY EGSON |
| Smoke Detectors | 11/3/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/15/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 12/15/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 12/15/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 12/15/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 12/15/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 12/15/2022 | SGSOV Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 12/28/2022 | Approved | ANTHONY EGSON |
| Final | 12/28/2022 | OK to Issue CofO | ANTHONY EGSON |
| Service/Power Release | 12/28/2022 | Approved | ANTHONY EGSON |