600 N MILO TER Unit 1-3 90042

Certificate Information: 600 N MILO TER Unit 1-3 90042

Application / Permit
20016-10000-20936
Plan Check / Job No.
B20LA15385
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CHANGE OF USE FROM CHURCH TO 3-UNIT APARTMENT AND INTERIOR REMODEL. NEW EXTERIOR FINISHES AND WINDOWS. (NFPA 13 SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2020 APPLICANT
Assigned to Plan Check Engineer 8/28/2020 GEORGE ALVAREZ
Corrections Issued 8/31/2020 GEORGE ALVAREZ
Applicant returned to address corrections 12/14/2020 RACHEL BEYENE
Applicant returned to address corrections 8/17/2021 FERNANDO FLORES
Applicant returned to address corrections 10/17/2021 AUNG SOE
Applicant returned to address corrections 10/28/2021 AUNG SOE
Plan Check Approved 11/1/2021 AUNG SOE
Issued 1/12/2022 APPLICANT
Building Plans Picked Up 1/13/2022 APPLICANT
CofO in Progress 5/15/2024 RAMAZANALI ALMASI
CofO Issued 5/15/2024 ERNESTO CORRAL
Permit Finaled 5/15/2024 ERNESTO CORRAL

Permit Application Clearance Information

DAS Clearance Cleared 8/18/2021 FARUK SEZER
Address approval Cleared 8/31/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/3/2021 JEANIE LAM
Sewer availability Cleared 9/16/2021 JEANIE LAM

Contact Information

Contractor L & T Construction Inc; Lic. No.: 878638-B PO BOX 1736      TEMPLE CITY, CA 91780
Engineer Lin,, Jason K; Lic. No.: S6095 1529 W LONGHILL DR      MONTEREY PARK, CA 91754

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 3/9/2022 Corrections Issued MARK FERRARI
Drywall Nailing 3/31/2022 Partial Inspection MARK FERRARI
Drywall Nailing 4/12/2022 Partial Inspection MARK FERRARI
Wood Frame 11/14/2022 Not Ready for Inspection MARK FERRARI
Footing/Foundation/Slab 12/12/2022 Partial Inspection MARK FERRARI
Deputy Drilled-In Anchors 12/14/2022 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 12/15/2022 Partial Approval JEROME BLACKWOOD
Wood Frame 12/22/2022 Partial Approval RAFAEL CORTES
Insulation 1/17/2023 Corrections Issued RAFAEL CORTES
Wood Frame 1/17/2023 Partial Approval RAFAEL CORTES
Insulation 1/23/2023 Approved RAFAEL CORTES
Wood Frame 1/23/2023 Approved RAFAEL CORTES
Drywall Nailing 2/6/2023 Approved RAFAEL CORTES
Interior/Exterior Lathing 2/15/2023 Approved RAFAEL CORTES
Footing/Foundation/Slab 4/3/2023 Not Ready for Inspection RAFAEL CORTES
Footing/Foundation/Slab 4/10/2023 Partial Approval RAFAEL CORTES
Deputy Drilled-In Anchors 4/11/2023 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 4/17/2023 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 4/21/2023 Partial Approval RAFAEL CORTES
Final 3/1/2024 Partial Approval RAMAZANALI ALMASI
SGSOV-Seismic Gas S/O Valve 3/1/2024 SGSOV Approved RAMAZANALI ALMASI
Smoke Detectors 3/1/2024 Approved RAMAZANALI ALMASI
Final 3/8/2024 Conditional Approval RAMAZANALI ALMASI
Final 5/15/2024 OK to Issue CofO RAMAZANALI ALMASI