600 N MILO TER Unit 1-3 90042
Certificate Information: 600 N MILO TER Unit 1-3 90042
- Application / Permit
- 20016-10000-20936
- Plan Check / Job No.
- B20LA15385
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CHANGE OF USE FROM CHURCH TO 3-UNIT APARTMENT AND INTERIOR REMODEL. NEW EXTERIOR FINISHES AND WINDOWS. (NFPA 13 SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofO Issued on 5/15/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/28/2020 | GEORGE ALVAREZ |
| Corrections Issued | 8/31/2020 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 12/14/2020 | RACHEL BEYENE |
| Applicant returned to address corrections | 8/17/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 10/17/2021 | AUNG SOE |
| Applicant returned to address corrections | 10/28/2021 | AUNG SOE |
| Plan Check Approved | 11/1/2021 | AUNG SOE |
| Issued | 1/12/2022 | APPLICANT |
| Building Plans Picked Up | 1/13/2022 | APPLICANT |
| CofO in Progress | 5/15/2024 | RAMAZANALI ALMASI |
| CofO Issued | 5/15/2024 | ERNESTO CORRAL |
| Permit Finaled | 5/15/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/18/2021 | FARUK SEZER |
| Address approval | Cleared | 8/31/2021 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2021 | JEANIE LAM |
| Sewer availability | Cleared | 9/16/2021 | JEANIE LAM |
Contact Information
| Contractor | L & T Construction Inc; Lic. No.: 878638-B | PO BOX 1736 TEMPLE CITY, CA 91780 |
| Engineer | Lin,, Jason K; Lic. No.: S6095 | 1529 W LONGHILL DR MONTEREY PARK, CA 91754 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 3/9/2022 | Corrections Issued | MARK FERRARI |
| Drywall Nailing | 3/31/2022 | Partial Inspection | MARK FERRARI |
| Drywall Nailing | 4/12/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 11/14/2022 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 12/12/2022 | Partial Inspection | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/14/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 12/15/2022 | Partial Approval | JEROME BLACKWOOD |
| Wood Frame | 12/22/2022 | Partial Approval | RAFAEL CORTES |
| Insulation | 1/17/2023 | Corrections Issued | RAFAEL CORTES |
| Wood Frame | 1/17/2023 | Partial Approval | RAFAEL CORTES |
| Insulation | 1/23/2023 | Approved | RAFAEL CORTES |
| Wood Frame | 1/23/2023 | Approved | RAFAEL CORTES |
| Drywall Nailing | 2/6/2023 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 2/15/2023 | Approved | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/3/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/10/2023 | Partial Approval | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 4/11/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Footing/Foundation/Slab | 4/17/2023 | Partial Approval | RAFAEL CORTES |
| Footing/Foundation/Slab | 4/21/2023 | Partial Approval | RAFAEL CORTES |
| Final | 3/1/2024 | Partial Approval | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Approved | RAMAZANALI ALMASI |
| Smoke Detectors | 3/1/2024 | Approved | RAMAZANALI ALMASI |
| Final | 3/8/2024 | Conditional Approval | RAMAZANALI ALMASI |
| Final | 5/15/2024 | OK to Issue CofO | RAMAZANALI ALMASI |