1039 1/2 N WILTON PL 90038

Certificate Information: 1039 1/2 N WILTON PL 90038

Application / Permit
20016-10000-20916
Plan Check / Job No.
B20LA15357
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** Convert existing garage (327 SF) to Accessory Dwelling Unit and one-story, ground floor addition (85 SF) to ADU. All work per WFPP.
Permit Issued
Issued on 3/11/2021
Issuing Office
Current Status
CofO Issued on 12/18/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/2/2020 APPLICANT
Assigned to Plan Check Engineer 9/24/2020 ARSALAN SHABESTARI
Corrections Issued 9/30/2020 ARSALAN SHABESTARI
Quality Review Completed 10/13/2020 PRANITA SHAH
Applicant returned to address corrections 11/21/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 1/19/2021 ARSALAN SHABESTARI
Plan Check Approved 1/21/2021 ARSALAN SHABESTARI
Issued 3/11/2021 APPLICANT
CofO in Progress 12/11/2021 STUART CHAPMAN
Permit Finaled 12/18/2021 DEROLD HAUFF
CofO Issued 12/18/2021 DEROLD HAUFF
Permit Finaled 12/18/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2020 JEANIE LAM
Roof/Waste drainage to street Cleared 10/9/2020 JEANIE LAM
Sewer availability Cleared 10/9/2020 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/14/2020 JEANIE LAM
Construction near power lines Cleared 12/23/2020 RIDWAN HARDY
Construction within easement Cleared 12/23/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/5/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 4/5/2021 Partial Approval CHRIS CHRISTENSEN
Pre-Inspection 4/5/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 4/5/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 5/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Rough 5/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 5/10/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/18/2021 Not Ready for Inspection CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/18/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 5/18/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 5/18/2021 Corrections Issued CHRIS CHRISTENSEN
PLUMBING-Rough 5/18/2021 Approved CHRIS CHRISTENSEN
BUILDING-Rough-Frame 5/25/2021 Corrections Issued CHRIS CHRISTENSEN
HVAC-Rough 5/25/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 5/25/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/18/2021 Approved JOSEPH MCGARRY
Insulation 6/18/2021 Approved JOSEPH MCGARRY
Drywall Nailing 6/21/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 6/21/2021 Approved CHRIS CHRISTENSEN
Sewer 8/20/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Sewer 8/26/2021 Approved CHRIS CHRISTENSEN
Gas Test 9/8/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/8/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 9/8/2021 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 11/24/2021 Approved CHRIS CHRISTENSEN
Final 11/24/2021 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 11/24/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 11/24/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 11/24/2021 Corrections Issued CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/24/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 11/24/2021 Approved CHRIS CHRISTENSEN
Final 12/10/2021 OK to Issue CofO STUART CHAPMAN
PLUMBING-Final 12/10/2021 Approved STUART CHAPMAN
Special/Order Compliance 12/11/2021 Approved STUART CHAPMAN