1500 S GRAMERCY PL 90019
Certificate Information: 1500 S GRAMERCY PL 90019
- Application / Permit
- 20016-10000-20841
- Plan Check / Job No.
- B20LA15266
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install Two Ordinary Moment Frames, Three Hardy Frame Shear Walls and Five Double Sided Shear Walls
- Permit Issued
- Issued on 11/5/2020
- Issuing Office
- Current Status
- CofC Issued on 5/14/2021
Permit Application Status History
| Submitted | 8/26/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2020 | VARAND SARKISIAN |
| Corrections Issued | 9/9/2020 | VARAND SARKISIAN |
| Quality Review Completed | 9/10/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 10/15/2020 | VARAND SARKISIAN |
| Plan Check Approved | 10/27/2020 | VARAND SARKISIAN |
| Issued | 11/5/2020 | APPLICANT |
| Permit Finaled-Status Void | 5/11/2021 | DARRYL ARNOLD |
| OK for CofC | 5/11/2021 | DARRYL ARNOLD |
| Re-Activate Permit | 5/12/2021 | DARRYL ARNOLD |
| CofC Issued | 5/14/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 10/6/2020 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 10/13/2020 | SAM NAVID |
| Miscellaneous | Cleared | 10/15/2020 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Tenant Habitability Plan | Cleared | 11/4/2020 | MICHAEL SOTO |
Contact Information
| Engineer | Namdar,, Mansour Tom; Lic. No.: NA2976 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 12/7/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 12/8/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 12/9/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 12/15/2020 | Approved | DARRYL ARNOLD |
| Pre-Inspection | 12/15/2020 | Approved | DARRYL ARNOLD |
| Structural Steel Frame | 12/15/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 12/17/2020 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 1/20/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 2/2/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 2/4/2021 | Conditional Approval | JONATHAN QUACH |
| Footing/Foundation/Slab | 2/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 2/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 2/16/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 2/22/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 2/22/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 2/22/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 2/24/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/2/2021 | Approved | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 3/9/2021 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/9/2021 | Corrections Issued | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 3/11/2021 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 4/12/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 4/12/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/27/2021 | Approved | DARRYL ARNOLD |
| Final | 5/11/2021 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 5/11/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/11/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/11/2021 | Approved | DARRYL ARNOLD |