2860 S HARCOURT AVE 90016

Certificate Information: 2860 S HARCOURT AVE 90016

Application / Permit
20016-10000-20832
Plan Check / Job No.
B20LA15259
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan check: NEW DETACHED ADU .Permit to Install a RADCO Approved Factory Built Housing Unit over a raised floor foundation.
Permit Issued
Issued on 11/18/2020
Issuing Office
Current Status
CofO Issued on 9/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 ARSALAN SHABESTARI
Corrections Issued 9/28/2020 ARSALAN SHABESTARI
Quality Review Completed 10/13/2020 PRANITA SHAH
Plan Check Approved 11/7/2020 ARSALAN SHABESTARI
Issued 11/18/2020 APPLICANT
CofO in Progress 8/23/2021 STUART CHAPMAN
Permit Finaled 9/29/2021 DEROLD HAUFF
CofO Issued 9/29/2021 DEROLD HAUFF
Permit Finaled 9/29/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/9/2020 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 10/9/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 10/9/2020 CECILIO NAVARRO
Sewer availability Cleared 10/9/2020 CECILIO NAVARRO
Construction near power lines Cleared 10/27/2020 RIDWAN HARDY
Construction within easement Cleared 10/27/2020 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/16/2020 Approved STUART CHAPMAN
Footing/Foundation/Slab 12/16/2020 Approved STUART CHAPMAN
Sewer 12/24/2020 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 2/17/2021 Approved STUART CHAPMAN
Green Building Rough 2/17/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 2/17/2021 Approved STUART CHAPMAN
Sewer 3/11/2021 Approved STUART CHAPMAN
Final 4/16/2021 Corrections Issued STUART CHAPMAN
Green Building Final 4/16/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Not Ready STUART CHAPMAN
Service/Power Release 4/16/2021 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 4/16/2021 Not Ready for Inspection STUART CHAPMAN
Final 4/28/2021 Corrections Issued DAVID FEILER
Green Building Final 4/28/2021 Not Ready for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 4/28/2021 SGSOV Approved DAVID FEILER
Service/Power Release 4/28/2021 Not Ready for Inspection DAVID FEILER
Smoke Detectors 4/28/2021 Not Ready for Inspection DAVID FEILER
Final 5/17/2021 Conditional Approval STUART CHAPMAN
Green Building Final 5/17/2021 Approved STUART CHAPMAN
Service/Power Release 5/17/2021 Approved STUART CHAPMAN
Smoke Detectors 5/17/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 8/20/2021 Approved STUART CHAPMAN
Final 8/20/2021 OK to Issue CofO STUART CHAPMAN
HVAC-Final 8/20/2021 Approved STUART CHAPMAN
PLUMBING-Final 8/20/2021 Approved STUART CHAPMAN