2505 S BUCKINGHAM ROAD 90016

Certificate Information: 2505 S BUCKINGHAM ROAD 90016

Application / Permit
20016-10000-20823
Plan Check / Job No.
B20LA15252
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
e-plan check:NEW DETACHED ADU . Permit to Install a RADCO Approved Factory Built Housing Unit over a raised floor foundation. FBH Per: RAD-31-1027 & RAD-31-1028.
Permit Issued
Issued on 11/18/2020
Issuing Office
Current Status
CofO Issued on 6/11/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/25/2020 APPLICANT
Assigned to Plan Check Engineer 9/17/2020 ARSALAN SHABESTARI
Corrections Issued 9/22/2020 ARSALAN SHABESTARI
Quality Review Completed 10/13/2020 PRANITA SHAH
Plan Check Approved 11/7/2020 ARSALAN SHABESTARI
Issued 11/18/2020 APPLICANT
CofO in Progress 5/25/2021 STUART CHAPMAN
Permit Finaled 6/11/2021 DEROLD HAUFF
CofO Issued 6/11/2021 DEROLD HAUFF
Permit Finaled 6/11/2021 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/28/2020 RENZ SORIANO
Address approval Cleared 9/30/2020 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 10/2/2020 RENZ SORIANO
Sewer availability Cleared 10/2/2020 RENZ SORIANO
Construction near power lines Cleared 10/6/2020 RIDWAN HARDY
Construction within easement Cleared 10/6/2020 RIDWAN HARDY

Contact Information

Contractor United Dwelling Construction Inc; Lic. No.: 1066382-B 8757 WASHINGTON BLVD      CULVER CITY, CA 90232

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/11/2020 Approved STUART CHAPMAN
Sewer 12/24/2020 Partial Approval STUART CHAPMAN
Sewer 1/25/2021 No Access for Inspection KATHRYN BUTTERWORTH
Wood Frame 2/1/2021 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 2/3/2021 Approved STUART CHAPMAN
Drywall Nailing 2/3/2021 Approved STUART CHAPMAN
ELECTRICAL-Rough 2/3/2021 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2021 Approved STUART CHAPMAN
Green Building Rough 2/3/2021 Approved STUART CHAPMAN
HVAC-Rough 2/3/2021 Approved STUART CHAPMAN
Insulation 2/3/2021 Approved STUART CHAPMAN
Interior/Exterior Lathing 2/3/2021 Approved STUART CHAPMAN
MERV13>=Rough 2/3/2021 Approved STUART CHAPMAN
PLUMBING-Rough 2/3/2021 Approved STUART CHAPMAN
Verify Sprinkler Sign Off 2/3/2021 Approved STUART CHAPMAN
PLUMBING-Rough 2/18/2021 Approved STUART CHAPMAN
Sewer 2/18/2021 Approved STUART CHAPMAN
Final 4/26/2021 Not Ready for Inspection STUART CHAPMAN
Green Building Final 4/26/2021 Not Ready for Inspection STUART CHAPMAN
MERV13>=Final 4/26/2021 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Not Required STUART CHAPMAN
Service/Power Release 4/26/2021 Not Ready for Inspection STUART CHAPMAN
Smoke Detectors 4/26/2021 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 5/18/2021 Approved STUART CHAPMAN
Final 5/18/2021 Corrections Issued STUART CHAPMAN
Green Building Final 5/18/2021 Approved STUART CHAPMAN
HVAC-Final 5/18/2021 Approved STUART CHAPMAN
MERV13>=Final 5/18/2021 Approved STUART CHAPMAN
PLUMBING-Final 5/18/2021 Approved STUART CHAPMAN
Service/Power Release 5/18/2021 Approved STUART CHAPMAN
Smoke Detectors 5/18/2021 Approved STUART CHAPMAN
Final 5/25/2021 OK to Issue CofO STUART CHAPMAN