1620 W 45TH ST 90062
Certificate Information: 1620 W 45TH ST 90062
- Application / Permit
- 20016-10000-20771
- Plan Check / Job No.
- B20LA15207
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* CONVERSION & GROUND FLOOR ADDITION OF (E) GARAGE TO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c) & (e). ALL WORK PER IB/P/BC 2020-004 WOOD FRAME PRESCRIPTIVE PROVISIONS "COMPLY WITH DEPARTMENT ORDER effective date 9/03/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 10/29/2020
- Issuing Office
- Current Status
- CofO Issued on 3/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | LAMAR DAVIS |
| Corrections Issued | 9/8/2020 | LAMAR DAVIS |
| Quality Review Completed | 9/14/2020 | TU HUA |
| Applicant returned to address corrections | 10/1/2020 | LAMAR DAVIS |
| Plan Check Approved | 10/14/2020 | LAMAR DAVIS |
| Issued | 10/29/2020 | APPLICANT |
| CofO in Progress | 3/10/2021 | ROBERT MCDOWELL |
| Permit Finaled | 3/18/2021 | DEROLD HAUFF |
| CofO Issued | 3/18/2021 | DEROLD HAUFF |
| Permit Finaled | 3/18/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/25/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/25/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 9/25/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 9/25/2020 | CECILIO NAVARRO |
Contact Information
| Contractor | 8a General Construction; Lic. No.: 1020625-B | 11660 EL GRANADA AVE LYNWOOD, CA 90262 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/1/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 12/1/2020 | Partial Approval | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 12/16/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Rough | 12/16/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 12/16/2020 | Approved | ROBERT MCDOWELL |
| Insulation | 12/21/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 12/21/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Shower Pan | 12/21/2020 | Not Ready for Inspection | ROBERT MCDOWELL |
| Drywall Nailing | 12/24/2020 | Approved | ROBERT MCDOWELL |
| Green Building Rough | 12/24/2020 | Approved | ROBERT MCDOWELL |
| Interior/Exterior Lathing | 12/24/2020 | Approved | ROBERT MCDOWELL |
| BUILDING-Rough-Frame | 2/16/2021 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 2/16/2021 | Approved | ROBERT MCDOWELL |
| Final | 2/16/2021 | Conditional Approval | ROBERT MCDOWELL |
| Green Building Final | 2/16/2021 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 2/16/2021 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 2/16/2021 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 2/16/2021 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 2/16/2021 | Approved | ROBERT MCDOWELL |
| Final | 3/10/2021 | OK to Issue CofO | ROBERT MCDOWELL |