6129 W FOUNTAIN AVE 90028
Certificate Information: 6129 W FOUNTAIN AVE 90028
- Application / Permit
- 20016-10000-20674
- Plan Check / Job No.
- B20LA15119
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (3) SPECIAL STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Current Status
- CofC Issued on 8/9/2021
Permit Application Status History
| Submitted | 8/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | DANIEL SANJUAN |
| Corrections Issued | 9/15/2020 | DANIEL SANJUAN |
| Quality Review Completed | 9/21/2020 | HANS SANTIAGO |
| Plan Check Approved | 11/6/2020 | DANIEL SANJUAN |
| Issued | 12/23/2020 | APPLICANT |
| OK for CofC | 8/6/2021 | BRUCE CAMPBELL |
| CofC Issued | 8/9/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 9/23/2020 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 10/22/2020 | DAVID URITA |
| Tenant Habitability Plan | Cleared | 11/30/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/16/2021 | Partial Inspection | JONATHAN QUACH |
| Deputy Reinf. Concrete | 3/23/2021 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 3/23/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 3/26/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 3/26/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 3/26/2021 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 3/30/2021 | Conditional Approval | FRED WOHLFARTH |
| Deputy Wood Construction | 3/30/2021 | Conditional Approval | FRED WOHLFARTH |
| Floor/Roof Diaphrgm/Shear Wall | 3/30/2021 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 3/30/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 3/30/2021 | Approved | MARK FERRARI |
| Wood Frame | 3/30/2021 | Approved | MARK FERRARI |
| Drywall Nailing | 4/5/2021 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 4/5/2021 | Approved | JONATHAN QUACH |
| Final | 8/6/2021 | OK for CofC | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 8/6/2021 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 8/6/2021 | Approved | BRUCE CAMPBELL |