1035 N ORLANDO AVE 90069
Certificate Information: 1035 N ORLANDO AVE 90069
- Application / Permit
- 20016-10000-20552
- Plan Check / Job No.
- B20LA15035
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- **ePlan** Convert the existing garage into an accessory dwelling unit per LAMC 12.22 A.33 (b)(5)
- Permit Issued
- Issued on 2/17/2021
- Issuing Office
- Current Status
- CofO Issued on 12/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | MONICA RAMIREZ |
| Corrections Issued | 9/8/2020 | MONICA RAMIREZ |
| Quality Review Completed | 9/14/2020 | TU HUA |
| Applicant returned to address corrections | 10/5/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/4/2021 | MONICA RAMIREZ |
| Plan Check Approved | 2/17/2021 | MONICA RAMIREZ |
| Issued | 2/17/2021 | APPLICANT |
| CofO in Progress | 11/23/2021 | CHRIS CHRISTENSEN |
| CofO Issued | 12/21/2021 | RONALD MYRICK |
| Permit Finaled | 12/21/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 10/16/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2020 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 1/20/2021 | RIDWAN HARDY |
Contact Information
| Contractor | A List Builders Inc; Lic. No.: 952112-B | 13237 CHANDLER BLVD SHERMAN OAKS, CA 91401 |
| Engineer | Rooks,, Bret H; Lic. No.: C63445 | 174 LOMA BONITA SAN LUIS OBISPO, CA 93401 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/17/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 3/17/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 4/6/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 4/6/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 4/6/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/15/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Rough-Elec/Plmb/HVAC | 4/15/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/4/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Rough | 5/4/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Underground Mechanical | 5/4/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 5/19/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 5/19/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 5/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 5/28/2021 | No Access for Inspection | CHRIS CHRISTENSEN |
| Insulation | 6/3/2021 | Corrections Issued | CALEB MEISTER |
| Drywall Nailing | 6/9/2021 | Approved | WILLIAM WREN |
| Insulation | 6/9/2021 | Approved | WILLIAM WREN |
| Shower Pan | 6/9/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 6/30/2021 | Approved | BENEVA JACKSON |
| Shower Pan | 6/30/2021 | Approved | BENEVA JACKSON |
| ELECTRICAL-Final | 11/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 11/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 11/17/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| HVAC-Final | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 11/17/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 11/22/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 11/22/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 11/22/2021 | Approved | CHRIS CHRISTENSEN |