218 S HIGHLAND AVE 90036
Certificate Information: 218 S HIGHLAND AVE 90036
- Application / Permit
- 20016-10000-20550
- Plan Check / Job No.
- B20LA15033
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New patio cover to main house. Proposed patio cover and new sliding door from SFD to patio per EOR
- Permit Issued
- Issued on 2/18/2021
- Issuing Office
- Current Status
- CofO Issued on 4/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2020 | MONICA RAMIREZ |
| Corrections Issued | 8/25/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/8/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/19/2020 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/5/2020 | YOUNG KIM |
| Applicant returned to address corrections | 11/6/2020 | HELEN NGUYEN |
| Plan Check Approved | 11/28/2020 | JOE VO |
| Plan Check Approved | 11/28/2020 | CARLOS MONTES |
| No Progress | 12/15/2020 | CARLOS MONTES |
| Plan Check Approved | 12/15/2020 | CARLOS MONTES |
| Issued | 2/18/2021 | APPLICANT |
| CofO in Progress | 4/19/2023 | STUART CHAPMAN |
| CofO in Progress | 4/19/2023 | SCOTT FINNILA |
| CofO in Progress | 4/21/2023 | RICHARD DOCKUS |
| Permit Finaled | 4/23/2023 | DEROLD HAUFF |
| CofO Issued | 4/23/2023 | DEROLD HAUFF |
| Permit Finaled | 4/23/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 11/4/2020 | SUKI GERSHENHORN |
| Hist. Property Cntrct Mgr Appr | Cleared | 11/4/2020 | SUKI GERSHENHORN |
| Roof/Waste drainage to street | Cleared | 11/5/2020 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/1/2020 | THOMAS LANG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2022 | Partial Inspection | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 6/23/2022 | Approved | ADAM ESCOTO |
| METHANE-Barrier | 6/23/2022 | Approved | ADAM ESCOTO |
| METHANE-Subgrade | 6/23/2022 | Approved | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 11/10/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/17/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 3/1/2023 | Approved | RICHARD DOCKUS |
| Final | 3/1/2023 | Corrections Issued | RICHARD DOCKUS |
| Interior/Exterior Lathing | 3/1/2023 | Approved | RICHARD DOCKUS |
| METHANE-Final | 3/1/2023 | Approved | RICHARD DOCKUS |
| METHANE-Rough | 3/1/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 3/1/2023 | Approved | RICHARD DOCKUS |
| Final | 3/8/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 4/19/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/21/2023 | OK to Issue CofO | RICHARD DOCKUS |