218 S HIGHLAND AVE 90036

Certificate Information: 218 S HIGHLAND AVE 90036

Application / Permit
20016-10000-20550
Plan Check / Job No.
B20LA15033
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New patio cover to main house. Proposed patio cover and new sliding door from SFD to patio per EOR
Permit Issued
Issued on 2/18/2021
Issuing Office
Current Status
CofO Issued on 4/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2020 APPLICANT
Assigned to Plan Check Engineer 8/24/2020 MONICA RAMIREZ
Corrections Issued 8/25/2020 MONICA RAMIREZ
Applicant returned to address corrections 10/8/2020 MONICA RAMIREZ
Applicant returned to address corrections 10/19/2020 MONICA RAMIREZ
Applicant returned to address corrections 11/5/2020 YOUNG KIM
Applicant returned to address corrections 11/6/2020 HELEN NGUYEN
Plan Check Approved 11/28/2020 JOE VO
Plan Check Approved 11/28/2020 CARLOS MONTES
No Progress 12/15/2020 CARLOS MONTES
Plan Check Approved 12/15/2020 CARLOS MONTES
Issued 2/18/2021 APPLICANT
CofO in Progress 4/19/2023 STUART CHAPMAN
CofO in Progress 4/19/2023 SCOTT FINNILA
CofO in Progress 4/21/2023 RICHARD DOCKUS
Permit Finaled 4/23/2023 DEROLD HAUFF
CofO Issued 4/23/2023 DEROLD HAUFF
Permit Finaled 4/23/2023 DEROLD HAUFF

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 11/4/2020 SUKI GERSHENHORN
Hist. Property Cntrct Mgr Appr Cleared 11/4/2020 SUKI GERSHENHORN
Roof/Waste drainage to street Cleared 11/5/2020 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 12/1/2020 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/18/2022 Partial Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 6/23/2022 Approved ADAM ESCOTO
METHANE-Barrier 6/23/2022 Approved ADAM ESCOTO
METHANE-Subgrade 6/23/2022 Approved ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Approved ADAM ESCOTO
ELECTRICAL-Rough 11/10/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 11/17/2022 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 3/1/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 3/1/2023 Approved RICHARD DOCKUS
Final 3/1/2023 Corrections Issued RICHARD DOCKUS
Interior/Exterior Lathing 3/1/2023 Approved RICHARD DOCKUS
METHANE-Final 3/1/2023 Approved RICHARD DOCKUS
METHANE-Rough 3/1/2023 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 3/1/2023 SGSOV Approved RICHARD DOCKUS
Smoke Detectors 3/1/2023 Approved RICHARD DOCKUS
Final 3/8/2023 Not Ready for Inspection RICHARD DOCKUS
Final 4/19/2023 Not Ready for Inspection STUART CHAPMAN
Final 4/21/2023 OK to Issue CofO RICHARD DOCKUS