15133 W SYLVAN ST 91411

Certificate Information: 15133 W SYLVAN ST 91411

Application / Permit
20016-10000-20517
Plan Check / Job No.
B20LA15021
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan. Convert existing accessory building (garage) to detached ADU per state law GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 11/23/2020
Issuing Office
Current Status
CofO Issued on 6/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/21/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 HELEN NGUYEN
Corrections Issued 8/30/2020 HELEN NGUYEN
Quality Review Completed 9/13/2020 PRANITA SHAH
Applicant returned to address corrections 10/23/2020 HELEN NGUYEN
Applicant returned to address corrections 11/4/2020 HELEN NGUYEN
Applicant returned to address corrections 11/16/2020 HELEN NGUYEN
Plan Check Approved 11/19/2020 HELEN NGUYEN
Issued 11/23/2020 APPLICANT
CofO in Progress 4/29/2021 MICHEL ABAJAN
CofO Issued 6/26/2021 MICHAEL SMITH
Permit Finaled 6/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/2/2020 ADRIAN CASTRO
Sewer availability Cleared 9/2/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/3/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2020 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 12/9/2020 Not Ready for Inspection JENNIFER RABUCHIN
Underground Mechanical 12/14/2020 Not Ready for Inspection JOHN HAYES
Footing/Foundation/Slab 12/18/2020 Approved MICHEL ABAJAN
Wood Frame 12/23/2020 Not Ready for Inspection DAVID MATSON
PLUMBING-Rough 12/24/2020 Partial Inspection DAVID MATSON
Underground Mechanical 12/24/2020 Approved DAVID MATSON
ELECTRICAL-Rough 1/14/2021 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 1/19/2021 Approved MICHEL ABAJAN
HVAC-Rough 1/19/2021 Order to Comply Issued MICHEL ABAJAN
BUILDING-Rough-Frame 1/25/2021 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 1/25/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/25/2021 Corrections Issued JENNIFER RABUCHIN
Insulation 1/27/2021 Not Ready for Inspection DAVID SANDOVAL
PLUMBING-Rough 1/27/2021 Approved DAVID SANDOVAL
Wood Frame 1/27/2021 Not Ready for Inspection DAVID SANDOVAL
Insulation 1/29/2021 Not Ready for Inspection MICHEL ABAJAN
Interior/Exterior Lathing 1/29/2021 Approved MICHEL ABAJAN
Wood Frame 1/29/2021 Approved MICHEL ABAJAN
Insulation 2/1/2021 Approved JENNIFER RABUCHIN
Special/Order Compliance 2/1/2021 Corrections Issued JENNIFER RABUCHIN
Drywall Nailing 2/8/2021 Approved CHARLES POWELL
Green Building Rough 2/8/2021 Approved CHARLES POWELL
Wood Frame 2/8/2021 Approved CHARLES POWELL
Shower Pan 2/12/2021 Approved DANIEL ORRANTE
Interior/Exterior Lathing 2/17/2021 Partial Inspection JOHN HAYES
BUILDING-Rough-Frame 3/11/2021 Conditional Approval MICHAEL TEMPLE
Final 3/11/2021 Corrections Issued MICHAEL TEMPLE
Green Building Final 3/11/2021 Not Ready for Inspection MICHAEL TEMPLE
METHANE-Final 3/11/2021 Not Ready for Inspection MICHAEL TEMPLE
METHANE-Rough 3/11/2021 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/11/2021 SGSOV Not Ready MICHAEL TEMPLE
Smoke Detectors 3/11/2021 Corrections Issued MICHAEL TEMPLE
BUILDING-Rough-Frame 3/19/2021 Approved ARTHUR SARGSYAN
Final 3/19/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 3/19/2021 Approved ARTHUR SARGSYAN
METHANE-Final 3/19/2021 Approved ARTHUR SARGSYAN
METHANE-Rough 3/19/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/19/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/19/2021 Approved ARTHUR SARGSYAN
Final 3/31/2021 Partial Approval JENNIFER RABUCHIN
Final 4/7/2021 Corrections Issued JOHN HAYES
Final 4/29/2021 OK to Issue CofO MICHEL ABAJAN