1812 W MIDDLETON PL 90062
Certificate Information: 1812 W MIDDLETON PL 90062
- Application / Permit
- 20016-10000-20479
- Plan Check / Job No.
- B20LA14999
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO EXISTING SFD PER WFPP
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- Permit Finaled on 8/28/2023
Permit Application Status History
| Submitted | 8/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | STARR CHEN |
| Corrections Issued | 9/25/2020 | STARR CHEN |
| Quality Review Completed | 10/7/2020 | HERNAN ARREOLA |
| Building Plans Picked Up | 10/13/2020 | APPLICANT |
| Applicant returned to address corrections | 2/25/2021 | STARR CHEN |
| Applicant returned to address corrections | 4/23/2021 | STARR CHEN |
| Plan Check Approved | 5/20/2021 | STARR CHEN |
| Issued | 5/20/2021 | APPLICANT |
| Permit Finaled | 8/25/2023 | SABAS ALONSO |
Permit Application Clearance Information
| Sewer availability | Cleared | 10/1/2020 | JUAN ASHTON |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | JUAN ASHTON |
| Hydrant and Access approval | Cleared | 12/3/2020 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 9/29/2022 | Not Ready for Inspection | RYAN SALAZAR |
| ELECTRICAL-Rough | 11/1/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 11/1/2022 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 11/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 11/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 11/10/2022 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 11/28/2022 | Approved | HORACE FULTZ |
| Insulation | 11/28/2022 | Partial Approval | HORACE FULTZ |
| ELECTRICAL-Rough | 12/1/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/1/2022 | Approved | SABAS ALONSO |
| Drywall Nailing | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 12/6/2022 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 12/9/2022 | Partial Approval | SABAS ALONSO |
| Interior/Exterior Lathing | 12/20/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 4/3/2023 | Partial Approval | SABAS ALONSO |
| Pre-Inspection | 5/19/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Final | 6/2/2023 | No Access for Inspection | LILIANA PORTILLO |
| Service/Power Release | 6/2/2023 | No Access for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 6/7/2023 | Not Ready for Inspection | SABAS ALONSO |
| Service/Power Release | 6/7/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 8/2/2023 | Corrections Issued | SABAS ALONSO |
| Final | 8/14/2023 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/14/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 8/14/2023 | Approved | SABAS ALONSO |
| Final | 8/25/2023 | Permit Finaled | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 8/25/2023 | SGSOV Approved | SABAS ALONSO |