648 N HAVERFORD AVE 90272
Certificate Information: 648 N HAVERFORD AVE 90272
- Application / Permit
- 20016-10000-20384
- Plan Check / Job No.
- B20LA14947
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE W/REC ROOM ABOVE TO ACCESSORY DWELLING UNIT WITH NO STRUCTURAL CHANGES PER ORDINANCE.
- Permit Issued
- Issued on 4/12/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/11/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/25/2020 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 8/25/2020 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Plan Check Approved | 2/22/2023 | MINA HABILI |
| Issued | 4/12/2023 | APPLICANT |
| CofO in Progress | 3/13/2024 | EVAN COOPER |
| Permit Finaled | 4/11/2024 | DANIEL ORRANTE |
| CofO Issued | 4/11/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/11/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2020 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2020 | SAUL GARCIA |
| Sewer availability | Cleared | 9/9/2020 | SAUL GARCIA |
| ZA Case | Cleared | 9/10/2020 | JOE LUCKEY |
| ZI | Cleared | 9/10/2020 | JOE LUCKEY |
| Construction near power lines | Cleared | 12/12/2020 | RIDWAN HARDY |
| Coastal Zone | Cleared | 2/22/2023 | SPENCER WEJROWSKI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Final | 11/7/2023 | Corrections Issued | EVAN COOPER |
| Final | 11/7/2023 | Corrections Issued | EVAN COOPER |
| Gas Test | 11/7/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 11/7/2023 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 11/7/2023 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/7/2023 | SGSOV Not Ready | EVAN COOPER |
| Shower Pan | 11/7/2023 | Corrections Issued | EVAN COOPER |
| Smoke Detectors | 11/7/2023 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/26/2024 | Approved | EVAN COOPER |
| Insulation | 1/26/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 3/13/2024 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 3/13/2024 | Approved | EVAN COOPER |
| Final | 3/13/2024 | OK to Issue CofO | EVAN COOPER |
| Gas Test | 3/13/2024 | Approved | EVAN COOPER |
| Green Building Final | 3/13/2024 | Approved | EVAN COOPER |
| Green Building Rough | 3/13/2024 | Approved | EVAN COOPER |
| HVAC-Final | 3/13/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/13/2024 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/13/2024 | SGSOV Approved | EVAN COOPER |
| Shower Pan | 3/13/2024 | Approved | EVAN COOPER |
| Smoke Detectors | 3/13/2024 | Approved | EVAN COOPER |