126 S UNION PL 90026

Certificate Information: 126 S UNION PL 90026

Application / Permit
20016-10000-20363
Plan Check / Job No.
B20LA14936
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (N) 5-SPECIAL STEEL CANTILEVERED COLUMNS
Permit Issued
Issued on 4/26/2021
Issuing Office
Current Status
CofC Issued on 12/8/2021

Permit Application Status History

Submitted 8/20/2020 APPLICANT
Assigned to Plan Check Engineer 9/2/2020 JESSE VIDUYA
Corrections Issued 9/15/2020 JESSE VIDUYA
Quality Review Completed 9/17/2020 HANS SANTIAGO
Applicant returned to address corrections 10/2/2020 JESSE VIDUYA
Applicant returned to address corrections 1/20/2021 JESSE VIDUYA
Plan Check Approved 1/26/2021 JESSE VIDUYA
Issued 4/26/2021 APPLICANT
OK for CofC 12/8/2021 BRUCE CAMPBELL
CofC Issued 12/8/2021 WINSTON DUNNING

Permit Application Clearance Information

Historic Resource Verification Cleared 12/3/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 12/4/2020 GRACIELA ACOSTA
Abandoned oil well Cleared 1/6/2021 MATTHEW CRAIG
Tenant Habitability Plan Cleared 4/1/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/13/2021 Approved DARRYL ARNOLD
Wood Frame 6/1/2021 Corrections Issued MARK FERRARI
Footing/Foundation/Slab 6/24/2021 Approved MARK FERRARI
Deputy Reinf. Concrete 6/25/2021 Conditional Approval MARK FERRARI
Structural Steel Frame 7/7/2021 Partial Inspection MARK FERRARI
Structural Steel Frame 10/4/2021 Approved BRUCE CAMPBELL
Wood Frame 10/4/2021 Conditional Approval BRUCE CAMPBELL
Deputy Wood Construction 10/14/2021 Conditional Approval BRUCE CAMPBELL
Structural Steel Frame 10/14/2021 Approved BRUCE CAMPBELL
Wood Frame 10/14/2021 Approved BRUCE CAMPBELL
Interior/Exterior Lathing 10/21/2021 Conditional Approval DARRYL ARNOLD
Final 11/17/2021 Corrections Issued BRUCE CAMPBELL
METHANE-Final 11/17/2021 Approved BRUCE CAMPBELL
SGSOV-Seismic Gas S/O Valve 11/17/2021 SGSOV Approved BRUCE CAMPBELL
Smoke Detectors 11/17/2021 Approved BRUCE CAMPBELL
Final 12/6/2021 Not Ready for Inspection BRUCE CAMPBELL
Final 12/8/2021 OK for CofC BRUCE CAMPBELL