3835 S GOLDWYN TER 90232
Certificate Information: 3835 S GOLDWYN TER 90232
- Application / Permit
- 20016-10000-20362
- Plan Check / Job No.
- B20LA14935
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing detached garage to ADU.
- Permit Issued
- Issued on 3/19/2021
- Issuing Office
- Current Status
- Issued on 3/19/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/21/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2020 | JOE VO |
| Corrections Issued | 9/23/2020 | JOE VO |
| Quality Review Completed | 10/6/2020 | MINYE PAK |
| Applicant returned to address corrections | 11/10/2020 | JOE VO |
| Applicant returned to address corrections | 12/15/2020 | JOE VO |
| Applicant returned to address corrections | 1/15/2021 | JOE VO |
| Applicant returned to address corrections | 1/26/2021 | JOE VO |
| Plan Check Approved | 3/9/2021 | JOE VO |
| Issued | 3/19/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/2/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 4/27/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 4/27/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/16/2021 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 8/24/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 8/24/2021 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 9/7/2021 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/7/2021 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/12/2021 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 10/12/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 10/12/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 10/12/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 10/12/2021 | Not Ready for Inspection | EVAN COOPER |
| Shower Pan | 10/12/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/22/2021 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/22/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Shower Pan | 10/22/2021 | Approved | JOHNNY MIRANDA |
| Insulation | 10/27/2021 | Approved | KRISTEN CAUSEY |
| Drywall Nailing | 11/1/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 11/1/2021 | Partial Approval | RYAN SALAZAR |
| Final | 12/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 12/20/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 12/20/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 5/19/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Final | 5/19/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/19/2022 | SGSOV Not Ready | KEVIN SARGSYAN |
| Smoke Detectors | 5/19/2022 | Not Ready for Inspection | KEVIN SARGSYAN |