1424 W 215TH ST 90501
Certificate Information: 1424 W 215TH ST 90501
- Application / Permit
- 20016-10000-20122
- Plan Check / Job No.
- B20LA14823
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT GARAGE AND STORE ROOM TO ADU
- Permit Issued
- Issued on 11/10/2021
- Issuing Office
- Current Status
- CofO Issued on 5/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/19/2020 | RAHEL BEYENE |
| Corrections Issued | 8/26/2020 | RAHEL BEYENE |
| Applicant returned to address corrections | 3/23/2021 | RAHEL BEYENE |
| Applicant returned to address corrections | 5/11/2021 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 6/25/2021 | TSE MING HUANG |
| Plan Check Approved | 9/29/2021 | RAHEL BEYENE |
| Issued | 11/10/2021 | APPLICANT |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| CofO in Progress | 5/20/2022 | EUGENE CASSIDY |
| Permit Finaled | 5/31/2022 | DEROLD HAUFF |
| CofO Issued | 5/31/2022 | DEROLD HAUFF |
| Permit Finaled | 5/31/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/5/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 10/5/2020 | CHINH DINH |
| Sewer availability | Cleared | 10/5/2020 | CHINH DINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/24/2022 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 1/27/2022 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 1/27/2022 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 1/27/2022 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 1/27/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 2/1/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 2/22/2022 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 2/28/2022 | Approved | EUGENE CASSIDY |
| Rough-Elec/Plmb/HVAC | 2/28/2022 | Approved | EUGENE CASSIDY |
| Structural Steel Frame | 2/28/2022 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 3/7/2022 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 3/7/2022 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 4/21/2022 | Approved | EUGENE CASSIDY |
| Final | 4/21/2022 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/21/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 4/21/2022 | Approved | EUGENE CASSIDY |
| Final | 5/10/2022 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/16/2022 | Approved | EUGENE CASSIDY |
| Final | 5/16/2022 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 5/16/2022 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 5/16/2022 | Approved | EUGENE CASSIDY |