5315 E BALTIMORE ST 90042

Certificate Information: 5315 E BALTIMORE ST 90042

Application / Permit
20016-10000-20075
Plan Check / Job No.
B20LA14757
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR AND EXTERIOR ALTERATION OF (E) SFD AND RECONFIGURE FLOOR PLAN. KITCHEN AND BATHROOM REMODEL. REMOVE BEARING WALL. REMOVE 26'3 X 25' PORTION OF EXISTING ROOF AT FRONT OF BUILDING AND REFRAME WITH TRUSSES. NEW 4'8" X 5'6" PORCH AT FRONT.
Permit Issued
Issued on 11/5/2020
Issuing Office
Current Status
Permit Finaled on 6/23/2021

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 AMIR DANAI
Corrections Issued 8/21/2020 AMIR DANAI
Applicant returned to address corrections 9/4/2020 GEORGE ALVAREZ
Applicant returned to address corrections 9/23/2020 SHANGQIN XIE
Plan Check Approved 11/4/2020 SAMUEL GONZALEZ
Issued 11/5/2020 APPLICANT
Building Plans Picked Up 11/12/2020 APPLICANT
Permit Finaled 6/22/2021 CRAIG VAUGHAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/2/2020 CECILIO NAVARRO
Grading Pre-Inspection Cleared 10/15/2020 BRIAN MILLER
Low Impact Development Cleared 10/16/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 10/20/2020 THOMAS LANG
GPI Written Notices Cleared 10/23/2020 AMIR DANAI

Contact Information

Contractor C S General Contracting Inc; Lic. No.: 947524-B 2654 VIEWRIDGE DR      CHINO HILLS, CA 91709
Engineer Farah,, Moheb Dawod; Lic. No.: C51477 1351 BALDYVIEW CIR      CORONA, CA 92882

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/11/2021 No Access for Inspection CRAIG VAUGHAN
Deputy Reinf. Concrete 1/19/2021 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 1/22/2021 Approved COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 3/3/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/9/2021 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/10/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/10/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 3/12/2021 Approved CRAIG VAUGHAN
Insulation 3/17/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 3/19/2021 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 3/19/2021 Approved CRAIG VAUGHAN
Wood Frame 3/19/2021 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 3/23/2021 Approved CRAIG VAUGHAN
HVAC-Rough 3/23/2021 Approved CRAIG VAUGHAN
Insulation 3/23/2021 Approved CRAIG VAUGHAN
Drywall Nailing 3/26/2021 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 3/26/2021 Approved CRAIG VAUGHAN
Shower Pan 3/26/2021 Approved CRAIG VAUGHAN
Final 6/1/2021 Corrections Issued COREY HUPP
SGSOV-Seismic Gas S/O Valve 6/1/2021 SGSOV Approved COREY HUPP
Smoke Detectors 6/1/2021 Approved COREY HUPP
ELECTRICAL-Final 6/22/2021 Approved CRAIG VAUGHAN
Final 6/22/2021 Permit Finaled CRAIG VAUGHAN
HVAC-Final 6/22/2021 Approved CRAIG VAUGHAN
PLUMBING-Final 6/22/2021 Approved CRAIG VAUGHAN