5601 N DE SOTO AVE 91367

Certificate Information: 5601 N DE SOTO AVE 91367

Application / Permit
20016-10000-19978
Plan Check / Job No.
B20LA14713
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
Eplan: The TI work involves replacement of existing mammography equipment with new in existing 3 rooms: Room 3819, Room 3923 & Room 3824. The replacement will occur over three phases and include structural anchorage, electrical and patch and repair of existing slab. Electrical scope will be submitted directly to engineering department.
Permit Issued
Issued on 9/28/2020
Issuing Office
Current Status
Permit Finaled on 3/9/2021

Permit Application Status History

Submitted 8/18/2020 APPLICANT
Assigned to Plan Check Engineer 8/18/2020 MONICA RAMIREZ
Corrections Issued 8/19/2020 MONICA RAMIREZ
Applicant returned to address corrections 9/2/2020 HELEN NGUYEN
Applicant returned to address corrections 9/14/2020 MONICA RAMIREZ
Plan Check Approved 9/22/2020 MONICA RAMIREZ
Issued 9/28/2020 APPLICANT
Permit Finaled 3/9/2021 ANDREW DORSO

Permit Application Clearance Information

Specific Plan Cleared 9/14/2020 SHEILA AHORAIAN
Specific Plan Cleared 9/18/2020 KRISTINE JEGALIAN
ZI Cleared 9/18/2020 KRISTINE JEGALIAN

Contact Information

Architect Rose,, Kirk; Lic. No.: C21753 2044 CORRAL CANYON ROAD      MALIBU, CA 90265
Contractor Kaiser Foundation Health Plan Inc; Lic. No.: 370871-B 4175 E LA PALMA AVE STE 200      ANAHEIM, CA 92807
Engineer Franco,, Richard; Lic. No.: S4886 25448 VIA JARDIN      VALENCIA, CA 91355

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/20/2020 Approved DANIEL VARNUM
Deputy Drilled-In Anchors 11/5/2020 Conditional Approval PAUL DAVIDSON
Final 11/10/2020 Partial Approval DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 11/10/2020 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 11/10/2020 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 1/14/2021 Approved HAMID PISHEHVAR
Final 3/9/2021 Permit Finaled ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 3/9/2021 SGSOV Approved ANDREW DORSO
Smoke Detectors 3/9/2021 Approved ANDREW DORSO