695 S SANTA FE AVE 150-A 90021

Certificate Information: 695 S SANTA FE AVE 150-A 90021

Application / Permit
20016-10000-19851
Plan Check / Job No.
B20LA14649
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
New tenant improvement and change of use from retail to tattoo parlor.
Permit Issued
Issued on 2/23/2021
Issuing Office
Current Status
Permit Finaled on 1/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2020 APPLICANT
Assigned to Plan Check Engineer 8/27/2020 HELEN NGUYEN
Corrections Issued 8/27/2020 HELEN NGUYEN
Applicant returned to address corrections 9/21/2020 ARSALAN SHABESTARI
Applicant returned to address corrections 1/4/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/21/2021 HELEN NGUYEN
Applicant returned to address corrections 2/2/2021 HELEN NGUYEN
Plan Check Approved 2/15/2021 JOE VO
Issued 2/23/2021 APPLICANT
Permit Finaled-Status Void 11/16/2021 DANIEL COLLINS
Re-Activate Permit 12/14/2021 DANIEL COLLINS
Permit Finaled 1/26/2022 ERNESTO CORRAL

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/2/2020 RENZ SORIANO
ZA Case Cleared 11/12/2020 RICHARD REASER
ZA Case Cleared 11/12/2020 RICHARD REASER
ZA Case Cleared 11/12/2020 RICHARD REASER
ZA Case Cleared 11/12/2020 RICHARD REASER
Historic Resource Verification Cleared 11/13/2020 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 11/13/2020 GRACIELA ACOSTA
Sewer availability Cleared 11/16/2020 RENZ SORIANO

Contact Information

Architect Powell,, Edward W; Lic. No.: C27775 1025 N VENTURA AVENUE      OAK VIEW, CA 93022
Contractor Barling Construction Inc; Lic. No.: 1023529-B 1920 VIOLET STREET SUITE 201      LOS ANGELES, CA 90021

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/3/2021 Approved RUSSELL BONVOULOIR
Light Gage Steel Frame 7/8/2021 Not Ready for Inspection MARK FERRARI
Light Gage Steel Frame 9/22/2021 Approved JONATHAN QUACH
Final 11/16/2021 Partial Inspection DANIEL COLLINS
Green Building Final 11/16/2021 Approved DANIEL COLLINS
SGSOV-Seismic Gas S/O Valve 11/16/2021 SGSOV No Gas DANIEL COLLINS
Smoke Detectors 11/16/2021 Approved DANIEL COLLINS