4436 N WOODMAN AVE 91423
Certificate Information: 4436 N WOODMAN AVE 91423
- Application / Permit
- 20016-10000-19606
- Plan Check / Job No.
- B20LA14497
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: SOFT STORY SEISMIC REINFORCEMENT AT BUILDING PARKING GARAGE USING (1) SPECIAL CANTILEVERED COLUMN & (4) HARDY FRAME STRONG WALLS WITH GRADE BEAMS.
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- CofC Issued on 1/8/2021
Permit Application Status History
| Submitted | 8/12/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/27/2020 | JESSE VIDUYA |
| Corrections Issued | 9/2/2020 | JESSE VIDUYA |
| Quality Review Completed | 9/4/2020 | HANS SANTIAGO |
| Applicant returned to address corrections | 9/15/2020 | JESSE VIDUYA |
| Applicant returned to address corrections | 9/23/2020 | JESSE VIDUYA |
| Plan Check Approved | 10/2/2020 | JESSE VIDUYA |
| Issued | 10/8/2020 | APPLICANT |
| OK for CofC | 1/8/2021 | MARK FERRARI |
| CofC Issued | 1/8/2021 | MARK FERRARI |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/8/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Retrofitting360 Inc; Lic. No.: 1039226-B | 19562 VENTURA BLVD# 230 TARZANA, CA 91356 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/29/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 11/20/2020 | Approved | JOE VELASQUEZ |
| Reinforced Concrete Frame | 11/20/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 11/20/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 11/20/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 11/23/2020 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 11/30/2020 | Approved | ANDREW DORSO |
| Wood Frame | 11/30/2020 | Approved | ANDREW DORSO |
| Interior/Exterior Lathing | 12/3/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 12/8/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 12/9/2020 | Approved | JOE VELASQUEZ |
| Final | 12/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/18/2020 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 12/18/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 12/22/2020 | Not Ready for Inspection | JEFFREY DURAN |
| SGSOV-Seismic Gas S/O Valve | 12/22/2020 | SGSOV Approved | JEFFREY DURAN |
| Smoke Detectors | 12/22/2020 | Approved | JEFFREY DURAN |
| Final | 1/8/2021 | OK for CofC | MARK FERRARI |