1147 S HOPE ST 90015

Certificate Information: 1147 S HOPE ST 90015

Application / Permit
20016-10000-19598
Plan Check / Job No.
B20LA14487
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT OF AN EXISTING OFFICE WITH MEZZANINE. URM BUILDING.
Permit Issued
Issued on 12/8/2020
Issuing Office
Current Status
Permit Finaled on 10/20/2021

Permit Application Status History

Submitted 8/13/2020 APPLICANT
Assigned to Plan Check Engineer 9/4/2020 MANUEL MONTUFAR
Corrections Issued 9/23/2020 MANUEL MONTUFAR
Quality Review Completed 9/23/2020 RODOLFO ARIAS
Building Plans Picked Up 9/28/2020 APPLICANT
Applicant returned to address corrections 10/9/2020 MANUEL MONTUFAR
Applicant returned to address corrections 10/20/2020 MANUEL MONTUFAR
Disabled Access Plans Picked Up 10/21/2020 APPLICANT
Green Plans Picked Up 11/18/2020 APPLICANT
Applicant returned to address corrections 12/1/2020 MANUEL MONTUFAR
Plan Check Approved 12/8/2020 MANUEL MONTUFAR
Issued 12/8/2020 APPLICANT
Permit Finaled 10/19/2021 TIMOTHY BUXTON

Permit Application Clearance Information

Historic Resource Verification Cleared 10/1/2020 MICAELA TORRES-GIL
"D" conditions Cleared 10/13/2020 ANACANY HURTADO
"Q" conditions Cleared 10/13/2020 ANACANY HURTADO
Redevelopment Project Area Cleared 10/23/2020 DAVID URITA
Green Code Cleared 11/5/2020 VIVIAN LAO
Eng Process Fee Ord 176,300 Cleared 11/19/2020 JEANIE LAM
DAS Clearance Cleared 12/1/2020 MANUEL MONTUFAR
Sewer availability Cleared 12/1/2020 JEANIE LAM

Contact Information

Architect Streshinsky,, David A; Lic. No.: C18642 24671 PALACE COURT      LAGUNA NIGUEL, CA 92677
Contractor Ayzar Inc; Lic. No.: 948731-B 1516 BROOKHOLLOW DRIVE STE B      SANTA ANA, CA 92705
Engineer Chen,, Jeff Y; Lic. No.: S4699 17500 REDHILL AVENUE SUITE 240      IRVINE, CA 92614

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/15/2020 Not Ready for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 1/25/2021 Not Ready for Inspection RONALD PACHECO
Footing/Foundation/Slab 1/25/2021 Not Ready for Inspection RONALD PACHECO
Excavation/Setback/Form/Re-Bar 1/28/2021 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 1/28/2021 Partial Approval KATY RAMIREZ
Footing/Foundation/Slab 2/8/2021 No Access for Inspection KATY RAMIREZ
Footing/Foundation/Slab 2/10/2021 Partial Approval KATY RAMIREZ
Deputy Wood Construction 2/11/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/12/2021 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 2/17/2021 Partial Inspection KATY RAMIREZ
Light Gage Steel Frame 3/3/2021 Partial Approval DANIEL COLLINS
Deputy Wood Construction 3/11/2021 Conditional Approval RONALD PACHECO
Light Gage Steel Frame 3/15/2021 Partial Approval DANIEL COLLINS
Wood Frame 3/15/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 4/5/2021 Partial Approval KATY RAMIREZ
Pre-Inspection 4/28/2021 Approved KATY RAMIREZ
Structural Steel Frame 4/28/2021 Not Ready for Inspection KATY RAMIREZ
Deputy Drilled-In Anchors 5/6/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/6/2021 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 5/7/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/7/2021 Conditional Approval KATY RAMIREZ
Drywall Nailing 5/11/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 5/25/2021 Partial Approval DANIEL COLLINS
Deputy Wood Construction 5/26/2021 Conditional Approval DANIEL COLLINS
Wood Frame 5/28/2021 Partial Approval DANIEL COLLINS
Wood Frame 6/2/2021 Not Ready for Inspection DANIEL COLLINS
Light Gage Steel Frame 6/18/2021 Approved KATY RAMIREZ
Pre-Inspection 7/16/2021 Partial Inspection KATY RAMIREZ
Smoke Detectors 7/29/2021 Approved BRUCE CAMPBELL
Final 8/3/2021 No Access for Inspection KATY RAMIREZ
Green Building Final 8/3/2021 No Access for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/3/2021 SGSOV Not Ready KATY RAMIREZ
Final 8/9/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 8/9/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Not Ready LANNY MERRICK
Special/Order Compliance 8/11/2021 Approved KATY RAMIREZ
Final 8/12/2021 Partial Approval KATY RAMIREZ
Green Building Final 8/12/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 8/12/2021 SGSOV Approved KATY RAMIREZ
Final 10/8/2021 Partial Approval TIMOTHY BUXTON
Final 10/19/2021 Permit Finaled TIMOTHY BUXTON