223 N BURLINGTON AVE 90026
Certificate Information: 223 N BURLINGTON AVE 90026
- Application / Permit
- 20016-10000-19527
- Plan Check / Job No.
- B20LA14431
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL (1) ordinary moment frame
- Permit Issued
- Issued on 11/6/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/25/2021
Permit Application Status History
| Submitted | 8/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2020 | DANIEL SANJUAN |
| Corrections Issued | 9/1/2020 | DANIEL SANJUAN |
| Quality Review Completed | 9/2/2020 | HANS SANTIAGO |
| Plan Check Approved | 9/17/2020 | DANIEL SANJUAN |
| Issued | 11/6/2020 | APPLICANT |
| OK for CofC | 1/19/2021 | MARK FERRARI |
| CofC Issued | 1/25/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 10/26/2020 | ISMAEL HERNANDEZ |
Contact Information
| Engineer | Shekaramiz,, Hamid; Lic. No.: C82784 | 2 TIMBRE RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/20/2020 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/25/2020 | Conditional Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/2/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 12/3/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 12/3/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 12/3/2020 | Partial Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 12/7/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 12/9/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 12/10/2020 | Partial Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 12/22/2020 | Corrections Issued | MARK FERRARI |
| Final | 1/19/2021 | OK for CofC | MARK FERRARI |
| METHANE-Final | 1/19/2021 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 1/19/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 1/19/2021 | Approved | MARK FERRARI |