1201 S HOPE ST #101 90015

Certificate Information: 1201 S HOPE ST #101 90015

Application / Permit
20016-10000-19499
Plan Check / Job No.
B20LA14421
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant - Take Out
Work Description
CHANGE OF USE FROM RETAIL TO TAKE OUT RESTAURANT. FIRST TENANT IMPROVEMENT.
Permit Issued
Issued on 12/11/2020
Issuing Office
Current Status
CofO Issued on 1/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/14/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 VU NGUYEN
Corrections Issued 9/17/2020 VU NGUYEN
Disabled Access Plans Picked Up 10/5/2020 APPLICANT
Quality Review Completed 10/9/2020 RODOLFO ARIAS
Green Plans Picked Up 11/9/2020 APPLICANT
Applicant returned to address corrections 12/8/2020 VU NGUYEN
Plan Check Approved 12/10/2020 VU NGUYEN
Issued 12/11/2020 APPLICANT
TCO Issued (Expire Date: 11-16-2021) 5/20/2021 DAVID TSAU
TCO Issued (Expire Date: 05-01-2022) 11/2/2021 ERNESTO CORRAL
TCO Issued (Expire Date: 10-26-2022) 4/29/2022 TED RIES
CofO in Progress 1/6/2023 KATY RAMIREZ
CofO Issued 1/11/2023 TED RIES
Permit Finaled 1/11/2023 TED RIES

Permit Application Clearance Information

Historic Resource Verification Cleared 10/22/2020 MICAELA TORRES-GIL
Green Code Cleared 10/28/2020 KHEDER ALRAZAA
Food Service Establishment Cleared 11/16/2020 KENNETH BROWNE
DAS Clearance Cleared 12/7/2020 VU NGUYEN
Redevelopment Project Area Cleared 12/8/2020 DAVID URITA
Food establishment approval Cleared 12/10/2020 LACDHS APPROVED

Contact Information

Architect Kelly,, George William; Lic. No.: C26144 1107 S WINDSOR BLVD      LOS ANGELES, CA 90019
Contractor Jungsco Inc; Lic. No.: 951264-B 1885 COMMONWEALTH AVE_UNIT B      FULLERTON, CA 92833

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 12/16/2020 Partial Approval KATY RAMIREZ
Drywall Nailing 12/18/2020 Corrections Issued KATY RAMIREZ
T-Bar Ceiling 3/9/2021 Partial Approval KATY RAMIREZ
Final 4/16/2021 Not Ready for Inspection KATY RAMIREZ
METHANE-Final 4/16/2021 Approved KATY RAMIREZ
METHANE-Rough 4/16/2021 Approved KATY RAMIREZ
Reinforced Concrete Frame 4/16/2021 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 4/16/2021 Approved KATY RAMIREZ
Special/Order Compliance 10/20/2021 Partial Inspection KATY RAMIREZ
Special/Order Compliance 4/6/2022 Approved TIMOTHY BUXTON
Special/Order Compliance 10/11/2022 Approved TIMOTHY BUXTON
Final 1/6/2023 OK to Issue CofO KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV No Gas KATY RAMIREZ