8919 N STANSBURY AVE 91402
Certificate Information: 8919 N STANSBURY AVE 91402
- Application / Permit
- 20016-10000-19365
- Plan Check / Job No.
- B20LA14341
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing garage and part of SFD into an Accessory Dwelling Unit.
- Permit Issued
- Issued on 2/2/2021
- Issuing Office
- Current Status
- CofO Issued on 1/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | JOE VO |
| Corrections Issued | 9/16/2020 | JOE VO |
| Quality Review Completed | 9/29/2020 | MINYE PAK |
| Plan Check Approved | 12/29/2020 | JOE VO |
| Issued | 2/2/2021 | APPLICANT |
| CofO in Progress | 1/10/2022 | MICHAEL TEMPLE |
| No Progress | 1/22/2022 | MICHAEL TEMPLE |
| CofO in Progress | 1/27/2022 | MICHAEL TEMPLE |
| CofO Issued | 1/29/2022 | MICHAEL SMITH |
| Permit Finaled | 1/29/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/20/2020 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/20/2020 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/13/2021 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/8/2021 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 5/26/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/26/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 5/26/2021 | Partial Approval | GREGG CUMMINGS |
| Sewer | 5/26/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/16/2021 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/16/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 7/16/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 7/16/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 7/16/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 7/26/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/11/2021 | Approved | MICHEL ABAJAN |
| Green Building Rough | 8/11/2021 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 8/25/2021 | Approved | JAVIER RAMOS JR |
| Insulation | 8/25/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/25/2021 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/25/2021 | Approved | JAVIER RAMOS JR |
| Final | 11/19/2021 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 11/19/2021 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 11/19/2021 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 11/19/2021 | Approved | GREGG CUMMINGS |
| Final | 12/6/2021 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 1/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 1/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 1/6/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/7/2022 | Approved | MICHAEL TEMPLE |
| Final | 1/7/2022 | OK to Issue CofO | MICHAEL TEMPLE |
| HVAC-Final | 1/7/2022 | Approved | MICHAEL TEMPLE |
| PLUMBING-Final | 1/7/2022 | Approved | MICHAEL TEMPLE |
| SGSOV-Seismic Gas S/O Valve | 1/7/2022 | SGSOV Approved | MICHAEL TEMPLE |
| Smoke Detectors | 1/7/2022 | Approved | MICHAEL TEMPLE |
| Special/Order Compliance | 1/24/2022 | Corrections Issued | MICHAEL TEMPLE |