8503 N DELCO AVE 91306
Certificate Information: 8503 N DELCO AVE 91306
- Application / Permit
- 20016-10000-19321
- Plan Check / Job No.
- B20LA14303
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert existing detached garage to accessory dwelling unit per state law GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | VU NGUYEN |
| Corrections Issued | 9/22/2020 | VU NGUYEN |
| Quality Review Completed | 9/25/2020 | RODOLFO ARIAS |
| Applicant returned to address corrections | 10/21/2020 | VU NGUYEN |
| Plan Check Approved | 1/19/2021 | VU NGUYEN |
| Issued | 1/25/2021 | APPLICANT |
| CofO in Progress | 11/12/2025 | CHRIS CHRISTENSEN |
| Permit Finaled | 11/19/2025 | JOHN JANSON |
| CofO Issued | 11/19/2025 | JOHN JANSON |
| Permit Finaled | 11/19/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 9/30/2020 | ABDULLAH SADOZAI |
| Sewer availability | Cleared | 9/30/2020 | ABDULLAH SADOZAI |
| CPC | Cleared | 10/1/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 10/1/2020 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2020 | ABDULLAH SADOZAI |
| Construction within easement | Cleared | 12/11/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/31/2021 | No Access for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 4/8/2021 | Partial Approval | DAVID STEPANYAN |
| PLUMBING-Rough | 4/8/2021 | Corrections Issued | DAVID STEPANYAN |
| Sewer | 4/8/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 4/30/2021 | Partial Approval | DAVID STEPANYAN |
| ELECTRICAL-Rough | 6/1/2021 | Not Ready for Inspection | TROY SANDERS |
| Insulation | 6/1/2021 | Not Ready for Inspection | TROY SANDERS |
| Interior/Exterior Lathing | 6/1/2021 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 8/2/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 9/30/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| HVAC-Rough | 9/30/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 9/30/2021 | Corrections Issued | DAVID STEPANYAN |
| ELECTRICAL-Rough | 10/13/2021 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 10/13/2021 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 10/19/2021 | Approved | TROY SANDERS |
| Green Building Rough | 10/19/2021 | Approved | TROY SANDERS |
| PLUMBING-Rough | 10/19/2021 | Approved | TROY SANDERS |
| Insulation | 12/9/2021 | Corrections Issued | JESUS PINEDA |
| Insulation | 12/22/2021 | Approved | ROBERT GOLD |
| Wood Frame | 2/3/2022 | Approved | JESUS PINEDA |
| Drywall Nailing | 2/16/2022 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 4/19/2022 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 4/19/2022 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 5/3/2023 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 6/16/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 7/26/2024 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 7/26/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/26/2024 | SGSOV Not Ready | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/26/2024 | Approved | CHRIS CHRISTENSEN |
| Final | 11/6/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Green Building Final | 11/6/2024 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 11/6/2024 | SGSOV Not Required | CHRIS CHRISTENSEN |
| Final | 2/4/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 2/4/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 2/18/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 7/9/2025 | No Access for Inspection | CHRIS CHRISTENSEN |
| Final | 10/21/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Pre-Inspection | 10/24/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 11/10/2025 | OK to Issue CofO | CHRIS CHRISTENSEN |