8503 N DELCO AVE 91306

Certificate Information: 8503 N DELCO AVE 91306

Application / Permit
20016-10000-19321
Plan Check / Job No.
B20LA14303
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Convert existing detached garage to accessory dwelling unit per state law GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 1/25/2021
Issuing Office
Current Status
CofO Issued on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/3/2020 VU NGUYEN
Corrections Issued 9/22/2020 VU NGUYEN
Quality Review Completed 9/25/2020 RODOLFO ARIAS
Applicant returned to address corrections 10/21/2020 VU NGUYEN
Plan Check Approved 1/19/2021 VU NGUYEN
Issued 1/25/2021 APPLICANT
CofO in Progress 11/12/2025 CHRIS CHRISTENSEN
Permit Finaled 11/19/2025 JOHN JANSON
CofO Issued 11/19/2025 JOHN JANSON
Permit Finaled 11/19/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 9/30/2020 ABDULLAH SADOZAI
Sewer availability Cleared 9/30/2020 ABDULLAH SADOZAI
CPC Cleared 10/1/2020 LAUREN PADICK
Miscellaneous Cleared 10/1/2020 LAUREN PADICK
Eng Process Fee Ord 176,300 Cleared 11/2/2020 ABDULLAH SADOZAI
Construction within easement Cleared 12/11/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/31/2021 No Access for Inspection DAVID STEPANYAN
Footing/Foundation/Slab 4/8/2021 Partial Approval DAVID STEPANYAN
PLUMBING-Rough 4/8/2021 Corrections Issued DAVID STEPANYAN
Sewer 4/8/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 4/30/2021 Partial Approval DAVID STEPANYAN
ELECTRICAL-Rough 6/1/2021 Not Ready for Inspection TROY SANDERS
Insulation 6/1/2021 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 6/1/2021 Partial Approval TROY SANDERS
ELECTRICAL-Rough 8/2/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 9/30/2021 Not Ready for Inspection DAVID STEPANYAN
HVAC-Rough 9/30/2021 Approved DAVID STEPANYAN
PLUMBING-Rough 9/30/2021 Corrections Issued DAVID STEPANYAN
ELECTRICAL-Rough 10/13/2021 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 10/13/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 10/19/2021 Approved TROY SANDERS
ELECTRICAL-Rough 10/19/2021 Approved TROY SANDERS
Green Building Rough 10/19/2021 Approved TROY SANDERS
PLUMBING-Rough 10/19/2021 Approved TROY SANDERS
Insulation 12/9/2021 Corrections Issued JESUS PINEDA
Insulation 12/22/2021 Approved ROBERT GOLD
Wood Frame 2/3/2022 Approved JESUS PINEDA
Drywall Nailing 2/16/2022 Approved JESUS PINEDA
PLUMBING-Rough 4/19/2022 Approved CHRIS CHRISTENSEN
Shower Pan 4/19/2022 Approved CHRIS CHRISTENSEN
Gas Test 5/3/2023 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 6/16/2023 Corrections Issued CHRIS CHRISTENSEN
Final 7/26/2024 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 7/26/2024 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 7/26/2024 SGSOV Not Ready CHRIS CHRISTENSEN
Smoke Detectors 7/26/2024 Approved CHRIS CHRISTENSEN
Final 11/6/2024 Not Ready for Inspection CHRIS CHRISTENSEN
Green Building Final 11/6/2024 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 11/6/2024 SGSOV Not Required CHRIS CHRISTENSEN
Final 2/4/2025 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/4/2025 SGSOV Approved CHRIS CHRISTENSEN
Final 2/18/2025 Not Ready for Inspection CHRIS CHRISTENSEN
Final 7/9/2025 No Access for Inspection CHRIS CHRISTENSEN
Final 10/21/2025 Corrections Issued CHRIS CHRISTENSEN
Pre-Inspection 10/24/2025 Approved CHRIS CHRISTENSEN
Final 11/10/2025 OK to Issue CofO CHRIS CHRISTENSEN