1200 N GETTY CENTER DR 90049

Certificate Information: 1200 N GETTY CENTER DR 90049

Application / Permit
20016-10000-19310
Plan Check / Job No.
B20LA14296
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(15) Telecommunication Transmitter - wireless
Work Description
SCL GETTY CENTER- NODE 4. VERIZON WIRELESS PROPOSES TO INSTALL NEW SMALL CELL EQUIPMENT/ ANTENNAS ON AN EXISTING COMMERCIAL STRUCTURE (GETTY CENTER BUILDING): INSTALL (1) N ANTENNA, INSTALL (2) N RRU, AND INSTALL (4) N PSU'S. ZA-2018-5878-CUW
Permit Issued
Issued on 9/14/2021
Issuing Office
Current Status
CofO Issued on 5/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2020 APPLICANT
Assigned to Plan Check Engineer 8/21/2020 GEORGE ALVAREZ
Corrections Issued 8/24/2020 GEORGE ALVAREZ
Plan Check Approved 1/29/2021 LUKE GONZALES
Issued 9/14/2021 APPLICANT
Building Plans Picked Up 9/17/2021 APPLICANT
CofO in Progress 5/13/2022 JOHN DODGE
CofO in Progress 5/13/2022 JOHN DODGE
Permit Finaled 5/13/2022 DAVID TSAU
CofO Issued 5/13/2022 DAVID TSAU
Permit Finaled 5/13/2022 DAVID TSAU

Permit Application Clearance Information

Miscellaneous Cleared 1/12/2021 JESSE RAMOS
Plan Approval Cleared 1/12/2021 JESSE RAMOS
ZA Case Cleared 1/12/2021 JESSE RAMOS
ZA Case Cleared 1/21/2021 JESSE RAMOS

Contact Information

Architect Rome,, Jeffrey Lee; Lic. No.: C20876 1715 PORT CHARLES PLACE      NEWPORT BEACH, CA 92660
Contractor Diversified Communications Services Inc; Lic. No.: 540890-B 1260 PIONEER ST      BREA, CA 92821
Engineer Zalzali,, Wissam; Lic. No.: C71655 74 FEATHER RIDGE      MISSION VIEJO, CA 92692

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Final 3/22/2022 Corrections Issued JOHN DODGE
Reinforced Concrete Frame 3/22/2022 Not Ready for Inspection JOHN DODGE
SGSOV-Seismic Gas S/O Valve 3/22/2022 SGSOV Approved JOHN DODGE
Smoke Detectors 3/22/2022 Approved JOHN DODGE
Final 4/20/2022 Corrections Issued JOHN DODGE
Reinforced Concrete Frame 4/20/2022 Corrections Issued JOHN DODGE
Final 5/11/2022 OK to Issue CofO JOHN DODGE
Reinforced Concrete Frame 5/11/2022 Approved JOHN DODGE