122 E CHANDLER ST 90744

Certificate Information: 122 E CHANDLER ST 90744

Application / Permit
20016-10000-19302
Plan Check / Job No.
B20LA14290
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED CONVERSION OF GARAGE TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A); ALL WORK PER WFPP ****"COMPLY WITH DEPARTMENT ORDER effective date 01/11/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 12/15/2020
Issuing Office
Current Status
CofO Issued on 7/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2020 APPLICANT
Assigned to Plan Check Engineer 8/12/2020 SINA KHOSRAVI
Corrections Issued 8/13/2020 SINA KHOSRAVI
Applicant returned to address corrections 9/23/2020 RICARDO RAMIREZ
Building Plans Picked Up 9/24/2020 APPLICANT
Plan Check Approved 10/21/2020 SHANGQIN XIE
Issued 12/15/2020 APPLICANT
CofO in Progress 7/19/2025 MICHAEL PELHAM
Permit Finaled 7/19/2025 RICHARD STEINBACH
CofO Issued 7/19/2025 RICHARD STEINBACH
Permit Finaled 7/19/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 10/7/2020 CHINH DINH
Sewer availability Cleared 10/7/2020 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 10/8/2020 CHINH DINH
ZA Case Cleared 10/8/2020 ANACANY HURTADO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/20/2021 Corrections Issued JOHN KLARIN
BUILDING-Rough-Frame 3/3/2021 Conditional Approval JOHN KLARIN
ELECTRICAL-Rough 3/3/2021 Approved JOHN KLARIN
PLUMBING-Rough 3/3/2021 Approved JOHN KLARIN
Interior/Exterior Lathing 3/10/2021 Approved JOHN KLARIN
Pre-Inspection 3/17/2021 Approved JOHN KLARIN
BUILDING-Rough-Frame 3/24/2021 Approved JOHN KLARIN
Final 3/24/2021 Corrections Issued JOHN KLARIN
Green Building Final 3/24/2021 Approved JOHN KLARIN
Green Building Rough 3/24/2021 Approved JOHN KLARIN
METHANE-Final 3/24/2021 Approved JOHN KLARIN
METHANE-Rough 3/24/2021 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 3/24/2021 SGSOV Approved JOHN KLARIN
Smoke Detectors 3/24/2021 Approved JOHN KLARIN
Final 4/28/2021 Corrections Issued JOHN KLARIN
Final 6/8/2021 Corrections Issued JOHN KLARIN
Final 9/27/2021 Not Ready for Inspection JOHN KLARIN
Final 7/19/2025 OK to Issue CofO MICHAEL PELHAM