3826 S WESTSIDE AVE 90008
Certificate Information: 3826 S WESTSIDE AVE 90008
- Application / Permit
- 20016-10000-19261
- Plan Check / Job No.
- B20LA14257
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- DETACHED 342 SF. GARAGE TO BE CONVERTED INTO ADU
- Permit Issued
- Issued on 11/26/2020
- Issuing Office
- Current Status
- Issued on 11/26/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 8/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2020 | ADAM HEGAZI |
| Corrections Issued | 10/26/2020 | ADAM HEGAZI |
| Building Plans Picked Up | 10/30/2020 | APPLICANT |
| Plan Check Approved | 11/18/2020 | GEORGE ALVAREZ |
| Issued | 11/26/2020 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 10/7/2020 | ELENA LOPEZ |
| Sewer availability | Cleared | 10/7/2020 | ELENA LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2020 | ELENA LOPEZ |
| Construction near power lines | Cleared | 11/5/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Valencia Construction Company; Lic. No.: 1015167-B | 12069 SMALLWOOD AVE DOWNEY, CA 90242 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/10/2021 | Conditional Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 3/22/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 3/22/2021 | Approved | DAVID FEILER |
| Green Building Rough | 3/22/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 3/22/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/23/2021 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/1/2021 | Conditional Approval | DAVID FEILER |
| PLUMBING-Rough | 4/1/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 4/12/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 4/12/2021 | Approved | DAVID FEILER |
| Sewer | 4/12/2021 | Approved | DAVID FEILER |
| Underground Mechanical | 4/12/2021 | Approved | DAVID FEILER |
| Insulation | 4/21/2021 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 4/21/2021 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 4/30/2021 | Conditional Approval | FREDDIE RIVERA |
| Green Building Rough | 4/30/2021 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 5/12/2021 | Approved | AMY COLIN |
| Pre-Inspection | 5/12/2021 | Partial Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 6/28/2021 | Approved | ALFREDO BALANDRA |
| BUILDING-Rough-Frame | 10/29/2021 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 10/29/2021 | Approved | ANTHONY EGSON |
| Final | 10/29/2021 | Conditional Approval | ANTHONY EGSON |
| Green Building Final | 10/29/2021 | Approved | ANTHONY EGSON |
| HVAC-Final | 10/29/2021 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 10/29/2021 | Approved | ANTHONY EGSON |
| Smoke Detectors | 10/29/2021 | Approved | ANTHONY EGSON |
| Service/Power Release | 1/3/2022 | No Access for Inspection | ANTHONY EGSON |
| Service/Power Release | 1/19/2022 | Corrections Issued | ANTHONY EGSON |
| Service/Power Release | 2/16/2022 | Corrections Issued | ANTHONY EGSON |